StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Who Pays for Data Center Extension Cords?

11/13/2024

1 Comment

 
Picture
Virginia is trying to shove the barn door closed after the horses escaped by holding a technical conference regarding its proliferation of data centers and who pays to provide their electric service.  Questions to be addressed include:
Whether certain transmission costs should be directly assigned to a new large-use customer class?
In other words, should Virginia create another rate class for electric service to "large users" (aka data centers) and assign them the cost of all the new transmission lines they make necessary?

Well, bravo, Virginia!  However, Virginia only has jurisdiction to assign the costs that are assigned to Virginia load serving utilities, like Dominion.  The cost allocation of these big lines is a federal responsibility under the jurisdiction of the Federal Energy Regulatory Commission (FERC).  FERC approves the assignment of costs made by regional grid operator PJM Interconnection.  PJM's current approved cost allocation methodology assigns the costs of lines 500kV and above to the entire PJM region.  The PJM region includes all or parts of 13 other states:  West Virginia, Maryland, Delaware, Pennsylvania, New Jersey, Kentucky, Ohio, Illinois, North Carolina, the District of Columbia, Indiana, Michigan and Tennessee.  When PJM orders a new line 500kV or above, it allocates the costs among all 13 states based on the percent of the entire system that state has used over the past year.  Every state in the region uses the PJM system, and every one of those states gets a portion of the cost.  Each state then assigns the costs to its electric consumers using state rate classes.  Virginia is thinking about taking its portion and charging it directly to the data centers that take service in Virginia.  

But what about all the costs for data center transmission lines that are assigned to other states?  The other states cannot charge them to Virginia's data centers, they can only charge them to the customers who take service in their own state.  We're all still stuck with the cost of transmission extension cords that serve Virginia's data centers.

How can this change?  It can only change at the federal level where PJM's transmission cost allocation formula is approved.  That's FERC's jurisdiction.  When consumers and consumer advocates asked FERC to make PJM change its cost allocation formula to make the state with the data centers needing new transmission responsible for their entire cost, they were rejected 2-1.  Only when the entire cost of the transmission gets allocated to the state where the data centers take service can it be properly allocated to the actual users of these new extension cords through the very process Virginia is currently proposing.  Virginia's proposal only passes Virginia's share of the transmission line costs to Virginia's data centers.  The data centers that need the new transmission are not taking service in those other states and therefore the other states have no choice but to allocate the costs of new transmission service for Virginia's data centers to their own consumers.

Perhaps Virginia should first be asking FERC to change PJM's cost allocation formula so that Virginia is responsible for the entire cost of their transmission needs.  Instead, Virginia is happy to be a parasite and let other state electric consumers pay the cost of serving their data centers.

When consumers and consumer advocates questioned PJM's cost allocations for its Window 3 projects last year, the majority of the Commissioners were of the opinion that since PJM's cost allocations are already set and the cost allocations for Window 3 followed that cost allocation scheme, the only thing the Commission could do was approve them.  However, Commissioner Christie had a different opinion (although he legally had to concur).  He thought that the Commission should take up the issue of who pays for state public policies that cause new transmission, such as building data centers, or closing fossil fuel power plants.
While this matter (and the November 2023 RTEP Order) both arise in PJM, the issue of the proper regional cost allocation for public policy-driven transmission projects is not confined to PJM, but is applicable across all of the nation’s multi-state RTOs.  Since RTOs are regulated by this Commission, I believe that the time has come for this Commission to take the lead in its convening role to initiate a proceeding, such as a Notice of Inquiry, a series of technical conferences, or by initiating an FPA section 206 proceeding outside this docket, posing such important questions, among others, as:  What is the proper definition of a public policy transmission project?  Does the definition of public policy transmission project need to be changed for purposes of regional cost allocation?  How should public policy transmission projects be cost-allocated in a multi-state RTO?  In my view the states themselves need to be at the forefront of deciding these questions, as it is their own state policies that are largely making these questions unavoidable, as these two recent PJM RTEP cases graphically illustrate.
So while Virginia is acting parochially to solve problems for its own ratepayers, it is avoiding asking FERC to weigh in on this issue and solve the transmission extension cord rate burden on other states.  What's it going to take to solve this issue at FERC?  The other states need to speak up to ask FERC to solve it.

Meanwhile, Virginia will be taking comments after it holds its technical conference on December 16.  You don't need to live in Virginia to submit a comment asking them to raise the issue at FERC so that ALL its data center extension cord costs are allocated to Virginia, who can then re-allocate them to the data centers.  Nothing is ever going to change unless the other states speak up.

Click here for more information about Virginia's technical conference, Case No. PUR-2024-00144.
1 Comment

How They Steal Your Power

9/2/2024

0 Comments

 
What's scarier to greedy corporate interests than a grassroots movement against their industry?  Your success!  Corporate interests, whether it's the electric transmission industry, housing, data centers, or any other invasive and destructive industry are terrified of being thwarted by grassroots movements in the communities where they want to make money.

Last week, a grassroots group opposed to a new transmission line through central Maryland took their fight to the industry at a conference celebrating the data center industry in Frederick, Maryland.  
But the well-publicized protest was anticipated by conference organizers, who met the challenge with attempts to steal the protestors' power.
Leaders of the Maryland Technology Council, which organized the daylong session, had anticipated the ruckus. They briefed conference attendees on protocols and strategies for coping with the protesters and insisted that the proposed power line project is not directly connected to the Quantum Loophole data center campus, which is in the early stages of development in Frederick County.
Let's examine this article using one of my favorite tools -- the seven common propaganda devices.  This tool is one of the oldest in the propaganda handbook.

The device employed most frequently by the conference organizers was "Name Calling."  

First example -- in the quoted paragraph above the demonstration was referred to as "the ruckus."  Protestors were also referred to as "noisy", a "flashmob", and "outraged".  A noisy, outraged, flashmob ruckus, a description that is intended to turn the reader against the protestors.  It's an ad hominem argument... don't pay any attention to what those people are saying because they are members of an unacceptable group.

​Protestors were also called uneducated.
While Quantum Loophole executives tried to talk to some of the protesters during the lunch hour, Rick Weldon, president of the Frederick County Chamber of Commerce, later said some of the demonstrators at the community college Thursday didn’t have access to all the relevant information — and that some would be tough to persuade.

“Frankly, no matter what the subject, they’re going to hold up a sign and yell at you because they don’t want anything to change,” he said.
...another name calling technique to marginalize you and steal your power.  I'm going to guess that Rick Weldon knows a lot less about MPRP than any one of the protestors, but he uses his position to create a presumption of superior knowledge.  The "education deficit" model has been a long time favorite of transmission project proponents.  They like to think that opposition to transmission only happens because the community doesn't have enough information to make a sensible decision.  However the opposite is actually true, the more you know about a proposed transmission project, the worse it sounds.  No amount of information or "education" can change the mind of a landowner threatened by new transmission ripping through his largest investment.

Uneducated outrage is how opponents were framed in order to make conference attendees see them as an unacceptable group who should not be acknowledged.

Meanwhile, conference organizers employed "Glittering Generalities" to boost their own position.  Jobs, school funding, dramatic growth in local businesses, Maryland's economy, land conservation, hiking and biking trails, and the most vague of all... a bright future!

Conference organizers also tried to sever Maryland's data centers from the MPRP.  Either they are uneducated themselves, or they are spinning a carefully crafted alternate reality.  Although Quantum Loophole's power supply is being provided by upgrading a dedicated transmission line to the old Eastalco plant, that doesn't mean QL won't benefit from MPRP.  Quantum Loophole's dedicated transmission line feeds power from the Doubs substation to Quantum Loophole.  Doubs is also the endpoint for the MPRP.  All power flowing through MPRP is delivered to Doubs, where it is transferred to the numerous lines feeding out of Doubs, including the one to Quantum Loophole.  Power from MPRP will absolutely be used at Quantum Loophole.  Could Quantum Loophole get as much power as it needed if MPRP was cancelled?  PJM Interconnection planned MPRP as one of several new 500kV transmission lines to serve data center load in Virginia and Maryland.  And since Quantum Loophole seems to support MPRP, it stands to reason they think they will benefit from it.

The public relations war is heating up.  But what will they say when those same protestors put down their protest signs and go inside the PSC to defend their properties through the legal process?  Will Quantum Loophole step up to defend MPRP?  Or will it use proxies to do so, such as labor unions and local business groups?  A different kind of war will break out at the PSC once the application is filed, and that's where the ultimate decision will be made.
0 Comments

Loudoun Pushes Data Center Burden Onto Neighboring States

8/21/2024

0 Comments

 
Picture
Loudoun County, Virginia, has the largest concentration of data centers in the world.  The world!  It also has the nickname "Data Center Alley."  Loudoun County has become gross with data centers, and continues building more.  The data centers are Loudoun County's cash cow, providing a third of its annual budget.  Loudoun County is also the wealthiest county in the nation.  The entire nation!  Loudoun County is home to the rich and, due to its proximity to Washington, D.C., the powerful as well.  The rich and powerful thought nothing of Loudoun destroying its eastern regions, tossing them on the altar of the data center cash cow.  After all, more data center tax revenue means less taxes for the rich and powerful in the western regions of Loudoun.  Out of sight, out of mind!  Living near nasty infrastructure was fine for the plebeians, as long as the benefits from hosting it flowed to the rich and powerful.

But then something happened... the data centers needed more resources than Loudoun County had.  Now, normal people in that situation would begin building the resources needed to feed their cash cow, but that's not how things are done in Loudoun.  Loudoun continued to build its data centers and expected the needed resources would come from neighboring states just like magic.  Except importing those resources come with consequences, like new transmission extension cords.  Perish the thought!  Transmission lines are fine for those other states that still *gasp* burn coal to create electricity to power Loudoun's data centers, but they absolutely cannot happen in Loudoun!  Loudoun is ruled by the rich and powerful, don't cha know, and they absolutely cannot be burdened with anything so ugly and gauche as an electric transmission line bringing power to their data centers.

So the rich and powerful grabbed their government servants by the scruff of their necks and demanded that the government make the bad stuff go away... or else!

The Loudoun County government and local elected officials began holding secret meetings with NextEra, other transmission companies, PJM, and Western Loudoun's Sacred Cows to find a way to push the transmission nasties out of Loudoun.  After all, aren't those other states lesser trash cans in service of the rich and powerful in Loudoun?  When other citizens who would be impacted by a transmission line re-route asked to be included in the meetings, they were purposely excluded.  And wouldn't you know it... that's exactly where the MARL transmission line ended up... on the property of the landowners who tried to be included in the secret government meetings.  Loudoun County met with and did the bidding of a handful of rich and powerful citizens to TAKE property from other citizens not as fortunate.  Pepe' Le Pew tells me that kind of discrimination stinks to high heaven!
Picture
And so the MARL transmission line got pushed out of Loudoun County and over into Frederick and Montgomery Counties Maryland.  Benefits for Loudoun, impacts for neighboring states.  

The re-route will cost everyone in PJM an additional $167M to spare the sacred cows in Loudoun.  Loudoun thought nothing of this, even though other towns who ask for transmission siting concessions are usually required to pay the difference.

I'm starting to understand why Loudoun is the wealthiest county in the U.S. -- it doesn't pay its own way.  Loudoun County takes from neighboring states like a parasitic worm.

And now here they go again, with another transmission line that Loudoun County has demanded be buried for a short section that abuts another group of Sacred Cow homes.  That's all fine and good, but the burial is going to cost an additional $423M, a project cost increase of 61%!  Between these two transmission projects, saving Loudoun will cost electric consumers in other states more than half a billion dollars!

And who pays for that?  Every last electric customer in the PJM region.  Both of these projects that disturb Loudoun's delicate sensibilities are regional reliability projects that are charged 50% to all PJM consumers based on their load share ratio, and the other 50% is charged to the "users" of the project, which spreads to neighboring states like West Virginia, Pennsylvania, and Maryland.  Virginia is only paying a portion of the cost of the new transmission extension cords to serve their data centers.  Any increase in costs will come out of the pockets of everyone in the PJM region.

So, how does Loudoun County think the burial of transmission lines near Landsdowne should be paid for?  
As for the excess cost, the County believes that a special customer class, made up of high-wattage customers, would be proper for the Commission to consider. The increase in electrical demand can be directly traced to the connection of an identifiable class of such high-wattage users to the grid. It is in the public interest for the Commission to shift the cost of undergrounding some of these lines to the high-wattage customers creating the demand for them.  
Well, that's a low-information expert for ya... Buddy Rizer doesn't know diddly about utility rates.  While Virginia *could* create a new rate class, it absolutely will not do so within this docket.  Asking for something like that is outside the bounds of this proceeding.  Therefore, Loudoun is not providing any way to pay for the excess cost.  And, even if Virginia created a new data center customer class to charge its share of the transmission extension cords to the data centers it hosts, that doesn't do a damned thing for the ratepayers in other states, who don't have any data centers (or data center classes) to charge their share of the excess cost of burying lines in Loudoun County in order to spare Loudoun any impacts.  It's another selfish suggestion on the part of Loudoun County.  And where was Loudoun County when we were arguing at FERC about whether Virginia's data centers should pick up the entire $5B cost of the Window 3 projects meant to serve them?  Nowhere.  It doesn't want to pay for the projects it has caused.  It just wants all the benefits without any of the impacts.

It's all over Buddy Rizer's testimony.  And for the rest of us who don't benefit from Loudoun's data centers, or keeping Loudoun free from invasive transmission projects, it's positively revolting!
buddy_rizer_testimony
File Size: 575 kb
File Type: buddy rizer testimony
Download File

The citizens of Loudoun County are expressing significant concern about the impact that further above-ground transmission lines will have on their community. With hundreds of miles of these lines already crisscrossing the County, citizens are hoping for a thoughtful approach to future development. Numerous comments from the community reflect a growing movement to explore alternatives to traditional transmission lines. Organizations such as the Lansdowne Conservancy, Waterford Foundation, Loudoun Transmission Line Alliance, and Piedmont Environmental Council have organized public meetings to oppose these proposals, driven by a strong desire to prevent overhead transmission lines from dominating the landscape and causing irreparable harm to historic, economic, and natural resources in Loudoun. The community opposition was key in PJM’s decision to approve an alternate route for delivery.
WHAT MEASURES CAN BE TAKEN TO PROTECT LOUDOUN COUNTY’S SCENIC ASSETS FROM THE IMPACT OF HIGH-VOLTAGE POWER LINES?
Where appropriate and feasible, undergrounding may provide a reliable and long- lasting energy transmission solution that is less prone to outages with minimal disruption to the look and feel of the community at large. This approach will preserve the landscape for current and future residents and maintain the history and beauty of the County. Additionally, it supports a reliable and sustainable path forward as Virginia works to meet its energy production and transmission goals. By placing power lines underground, impact to scenic assets can be minimized while ensuring a resilient and efficient power infrastructure.

Picture
Don't get me wrong... I don't believe anybody should be impacted by transmission lines.  And that's the difference between me and Loudoun County... Loudoun County seems to think that only its special residents should be free from the impacts of its data center extension cords.  Loudoun County is perfectly okay with impacts to landowners in West Virginia, Pennsylvania and Maryland.  Loudoun County isn't advocating for its extension cords to be buried in those other states.  Those people simply don't matter to Loudoun County, except when they pay the extra cost of keeping Loudoun transmission line free.

It's about time that Loudoun started shouldering its own data center burden.  The data center transmission problem is completely of Loudoun County's making.  It could end it in a hot minute by putting a moratorium on data centers.  It could also solve it by building some new electric generators in Loudoun near the data centers.  Why don't you do these things instead of taking from neighboring states to fill your own coffers, Loudoun County?  Solve your own problem!  Your neighbors are quite sick of your hubris.  Here's a little advice from one of your favorite people!
Picture
0 Comments

How PJM and FERC Caused Huge Spikes in Regional Power Bills and New Transmission

8/9/2024

2 Comments

 
Picture
PJM's recent capacity auction resulted in huge price spikes in the cost of supplying power to electric customers in the PJM region for the 2025-2026 year.  It was directly caused by the actions of PJM and FERC.  These entities aren't protecting ratepayers, they are harming them!  Let me explain...

PJM holds annual capacity auctions to secure the provision of electricity three years in advance.  A capacity auction is not actual electricity, it is a promise from a generator to supply a certain amount of energy at a future point in time.  This is how PJM ensures that it will have enough electricity supply available three years from the auction.  PJM is paying these generators to be available to produce energy when needed during the auction year.  PJM starts by announcing a certain amount of electricity is needed for the auction year.  Generators submit bids of how much it will cost to be standing by to produce that electricity during the auction year.  PJM stacks the bids by price, and each bid is represented by an amount of electricity and a price.  PJM then looks at its bid stack and finds the place where the capacity need is met.  Whatever the price of that bid is the clearing price for all the capacity bids lower in the stack.  Those bids that go over the capacity price are not accepted.  At the end of the auction, PJM has a stable of committed generators sure to provide the power when needed 3 years from the auction date.

PJM does not order generation.  Generation is a market construct, where generators build when the capacity prices are profitable.  If the clearing price at auction is high, it would entice the development of new generation.  If the clearing price is low, many generators may not have enough revenue to continue to operate at a profit.  This is how PJM manages generation to make sure there is always enough, but not too much.  The auction serves as an important warning bell... when clearing prices are high, it means more generation needs to be built.  The auction sends a signal to generators to build more when the prices are high.  More generators lowers prices because there is more competition in the supply.  But what happens when the prices are high at the auction and no new generators get built?  That's exactly what just happened... there is a dearth of needed generation in PJM so prices shot through the roof to record highs.

The problem here began with PJM making a proposal to change the parameters of its auction.  In order to do so, it needed FERC's permission.  A battle broke out at FERC, with many other parties objecting to the auction changes.  FERC moves at a snail's pace and can take years to make a decision on a request.  The more parties to a case, the longer it takes to resolve it.

Because of the battle going on at FERC, the auctions got put on hold.  As Power magazine says, 
BRA auctions are usually held three years in advance of the delivery year. While the 2025/2026 auction was originally scheduled to be held in May 2022, it was suspended while the Federal Energy Regulatory Commission (FERC) considered the approval of new capacity market rules. The recent July 2024 auction stems from a compressed schedule that aims to return to the three-year forward basis. According to PJM, the next BRA—for the 2026/2027 delivery year—is scheduled for December 2024.
FERC suspended PJM's capacity auctions while it resolved the issue.  That's like turning off the warning system.  PJM's annual capacity auction couldn't send the market signal to build new generation because it wasn't being held.

During this time, an extreme change in the power needs of the PJM region was underway.  Many baseload fossil fuel generators closed, either the result of the last auction's low capacity prices, or because they were "dirty" and no longer socially acceptable.  The new generation that entered the market could not keep up with the amount of generation that was closing.  As a result, we had less generation available.  Also during this time, the building of new data centers and increasing power demands for AI shot through the roof.  No new generation to supply power for these data centers was proposed or built because PJM's auction warning bell was not sounding due to the auctions being suspended.

PJM used the only tool it had available to meet regional need... transmission.  PJM conducted a competitive transmission window to connect the remaining generators with the new data center load.  Unfortunately, the majority of the available generators are located in WV and PA, and the data center load is in Northern Virginia.  PJM asked for new transmission to connect the two, and it ended up with a whole bunch of new projects, including MARL and MPRP.  PJM says they are "needed" to supply power to the data centers because no new generation has been built anywhere near the data centers.

Now that FERC has finally resolved the issue and PJM has its new market parameters, PJM recently began holding auctions again.  The first new auction for the 2025-2026 year was held just 10 months before the auction year begins, instead of 3 years in advance.  There's no way new generators can be built in 10 months, even if the prices are generous enough to support them economically.  That's why the auction is always held 3 years in advance, in order to give time for new generation to be built to reduce auction prices.

Instead, we're looking at a transmission bandaid to keep the existing generation flowing to the places that need it.  And PJM has opened another transmission planning window to add another 4,500MW of generation imports to Northern Virginia because there is no generation currently proposed to fill that need.

Eventually, if PJM's market signal works as intended, new generation will be built near the load.  However, certain states like Virginia and Maryland have passed laws that prevent the building of new fossil fuel generation.  That leaves only the nuclear option to supply the outrageous amount of power needed by the data centers.  Can you imagine how long it would take to build a new nuclear plant in Northern Virginia?  It would be completed on the 12th of Never.  Meanwhile, transmission is the only viable option.

PJM's market system didn't work to get generation built in time to meet new need because PJM and FERC had turned it off and were asleep at the switch.  Now we have a disaster of epic proportions on our hands.

What's going to happen first?  The construction of hotly opposed transmission projects, or the building of new generation?  And where will that generation be built?  Continuing to build in PA and WV only perpetuates the transmission problem.  We need new generation at load.  It's probably cheaper than billions of dollars of new transmission, but it takes a willingness to sacrifice for its own benefit on the part of the data center loving states.

New generation is coming to market... and how much of it will obviate the need for new transmission?  That's an unknown at this point, but it's going to happen.  PJM's transmission project needs will change and fall apart.  Let's hold the line, folks!  This battle is far from over!
2 Comments

PJM Opens New Transmission Window To Serve Data Centers

7/15/2024

0 Comments

 
Here we go again!  

As if all the new transmission that came out of PJM's 2022 Window 3 isn't enough already, guess what?  PJM miscalculated.

That's right... the data center load in Northern Virginia is much bigger than PJM thought when it planned and selected a bunch of new transmission projects last year.

Here's PJM's latest plan.

PJM shared at its TEAC meeting last week that it was going to open a new window for transmission to import an additional 4,500MW of generation to "data center alley."  This time, the generation is supposed to come from wind, solar, and storage in Illinois.  Illinois, people!  Numerous new transmission lines from the Midwest to Loudoun County, Virginia.  That's 700 miles of new transmission!

How is it supposed to get there?  PJM burned up all its existing transmission corridors last time by using up the Doubs-Goose Creek corridor to save the Sacred Cows.  There won't be any new transmission going through Doubs this time around.  There also won't be any new transmission coming from the east.  Seems Pennsylvania is tapped out for exports this time around.

PJM claims:
Most of the additional generation required to meet load growth 2028 vs 2029 is sourced from PJM West.
That's going to look like this:
Picture
PJM is targeting new project approvals for this window at the end of this year so that transmission owners can get started failing at building them next year.

Sometimes, I get up in the morning and wonder if PJM is just punking us all by pretending that all this new transmission can actually get built.  When project after project fails, the data centers causing this problem are going to leave for more powerful pastures elsewhere, and then PJM can shrug and say, "Well, we tried!"

It's time to start participating in TEAC meetings again.  I'm sure they've missed all of us these past couple months...  see ya there!
0 Comments

PJM Sets A Precedent

7/15/2024

0 Comments

 
At its July 9 Transmission Expansion Advisory Committee meeting, PJM proposed a re-route of the MidAtlantic Resiliency Link (MARL).  MARL is a giant extension cord for importing West Virginia coal-fired electricity to Loudoun County's "data center alley." 

Loudoun County just can't stop approving new data centers, even though it has no way to power them.  Now Loudoun's data center addiction is impacting people in other states... people who will have their property taken using eminent domain so that Loudoun can have more electricity for its data centers.  Loudoun County is not going to stop building data centers until its voters MAKE them stop building data centers.  That would happen in a hot minute if Loudoun County's SACRED COWS were impacted by the data centers.

This is the Sacred Cow Zone.  A look at an electric infrastructure map shows a pristine donut hole surrounded by high voltage transmission lines, substations, and generators on all sides.  But there's nothing in the Sacred Cow Zone!
Picture
What's a Sacred Cow?  A person with more money (and therefore more political influence) than you.  Examples include Jackie Kennedy, who took umbrage at a proposal to run a power line through her pony club in the Sacred Cow Zone back in the 1960's.  Legend has it that caused the line to end up in Jefferson County, West Virginia instead.  It's the reason we have that 500kV transmission line right across the middle of our county today.  Another example might be the movie stars and their wine-making friends who objected to a different 500kV high-voltage transmission line in the mid 2000s called TrAIL.  That line got pushed south into Fauquier County instead of impacting the Sacred Cows.

If you want to nauseate yourself a bit you could read the fakeass "report" the Sacred Cows threw together to plead their case that they are much, much too sacred to be impacted by the MARL.  They really think they are much more special than you.  Their views!  Their wine!  Their horses! Their environment!  They even claim to be DC's "central park", where harried rich and important people can go to escape the daily grind of grinding the less fortunate into the dirt.  If they thought they were going to get some sympathy from that report, I suggest it's time to buy a mirror and take a really good look.  Your arrogance is showing and people are laughing at your utter snobbery.  Get over yourself!

Because of Jackie Kennedy's pony club and resident movie stars, PJM was also attuned to the history of the Sacred Cow Zone.  It created a "work around" re-route up front, and now it has pulled the ejector button before even TRYING to propose a route through Loudoun.  It went from this
Picture
to this
Picture
It's a miracle!  The Sacred Cow Zone has been saved again!  However, in doing so, other landowners who were not previously affected are now affected.  In fact, those landowners in Northern Loudoun will have their property taken using eminent domain to widen the existing right of way, as confirmed by FirstEnergy's representative at the meeting.  Those sacrificial lambs get no consideration because they are not rich or important.

You may find it surprising that the Sacred Cow Zone is more important than the C&O Canal National Historical Park!  The re-route crosses the C&O twice whereas the original route didn't cross it at all.  Let's trash a national historical park that regular people from all over the region visit to escape snobbery and selfishness... in favor of snobbery and selfishness.  Is the Sacred Cow Zone really more important than a national park?

What is not really surprising is that the Sacred Cows didn't even think about using their Sacred status to actually help others.  Maybe if they did, they wouldn't be sacred anymore?  In exchange for continuing their Sacred status, the Cows proclaimed their mission:  

To support the overall PJM Regional Transmission Expansion Plan (RTEP) to inter alia supply the rising power needs of the region’s data center industry

Keep that in mind... the Sacred Cows love PJM, transmission lines, and data centers... as long as they are Not In My Back Yard!

And the whole debacle is going to cost all ratepayers in the region $167 MILLION more!  We're going to have to pay $167M to keep the Sacred Cows sacred and free from all that nasty infrastructure needed to power the data centers that keep their tax burden low.  What a world!

The real irony here may be the fact that a transmission line necessary for Loudoun's data centers has been pushed out of Loudoun and onto landowners in other states.
PJM claims it is not setting a precedent by re-routing a transmission line to spare certain rich and powerful people and dump it on others without the resources to fight back.

How are you enjoying the email bombardment, PJM?  The Sacred Cows just couldn't wait to strut their arrogance for the people impacted by the Maryland Piedmont Reliability Project and assure them that if they, too, started having a tantrum at PJM that they could have the transmission line moved out of their community, also.

See?  I'm already right about that.  PJM IS setting a precedent that if you don't want a transmission line in your community you simply have to make some demands and pull the ejector button and you're spared, like magic!  But if PJM is NOT setting a precedent, like Stu assured me they were not last week, then PJM is going to have to explain to those folks in Maryland why they are not Sacred Cows that deserve special treatment.  What'll it be, PJM?
0 Comments

Why Can't We Use Existing Rights-of-way for MPRP?

7/13/2024

3 Comments

 
This question has been asked over and over and the answer is multi-faceted and much too long for Facebook.

First, let's acknowledge that existing transmission lines in the region are serving a purpose.  They are providing a public service to provide electricity to customers.  Public utilities have service territories, where they either generate power or buy power to serve their customers.  They may own some of the transmission lines in their service territory, but sometimes another utility may own a line through their territory that was constructed to serve its own customers elsewhere.  You would have to do some research to find out who owns any particular transmission line you see.

A utility owns both the transmission line and the existing easement or property it sits on.  The easement has to be a certain size to meet safety code requirements.  The bigger the lines, the bigger the easement.  The utility has exclusive rights to the easement it owns, and the transmission lines on it.  The company paid for and constructed that line, and it was only allowed to take the amount of land it needed for the line, and no more.  The cost of this public service is reimbursed to the company by ratepayers who use it.

When the line needs repairs, the company that owns it is responsible.  When the line needs to be upgraded, the company that owns it is responsible.  Under current law, a company would have "first dibs" to upgrade or expand its line when it's needed.  Some have asked why PSEG cannot use eminent domain to take another company's line and use the land for the MPRP?  Utilities are immune to eminent domain in most cases.  Isn't it ironic, since they can use it on us?  Utilities are immune to eminent domain because they are providing a public service on that land.  If another entity was allowed to take that land from them, there wouldn't be a transmission line and the public service of providing electricity would end.  I'm sure you can appreciate that nobody is going to take the lines that serve you.

Therefore, PSEG has no right to take another company's transmission line that is in use and tear it down to erect their own line.  Heck, PSEG is not even a legal public utility in Maryland and has no utility rights at all at this time.  If that line needs to be rebuilt, the company that owns it has "first dibs" to rebuild it on the easement it already owns.

Some have asked why PSEG can't just hang some new wires on the existing towers owned by another utility?  Because those towers were not designed to carry that extra circuit.  Transmission towers are structurally engineered to carry the load they are designed for.  They are the property of the utility that owns them to use to maintain and expand its own system when needed.  If BGE was ordered to let PSEG use its transmission system for its own line, what would happen when BGE needed another line?  It would have to take a new right-of-way, since PSEG had used theirs for its own line.  PSEG cannot own a line that is on someone else's right-of-way.  Furthermore, it would be unsafe to try to string some new lines on a tower that doesn't even have a place to put them.  Sometimes, transmission companies think ahead a bit and build oversized towers that leave room for a future circuit to be added.  That is not the case in the MPRP area.  

So, what is PSEG doing in Maryland anyhow if they're not a public utility that serves customers in the state?  Our regional transmission system is operated and planned by a regional transmission operator called PJM Interconnection.  PJM makes sure the system is safe and reliable and that your lights stay on.  PJM is constantly monitoring its system, which consists of transmission lines owned by many of its members, like BG&E, or PSEG.  PJM runs a robust planning process and orders new lines, upgrades, and rebuilds that are recommended by its Transmission Expansion Advisory Committee (TEAC).  TEAC meetings are held once a month, and are open to the public.  But most of what PJM talks about is way too complicated for regular people and they are generally not involved.

Last year, PJM opened a new planning window to find transmission solutions to a reliability problem caused by 7,500MW of increased data center load in Northern Virginia, combined with 11,000MW of generation closing around the region.  Numerous companies submitted 72 different project ideas for PJM's consideration.  For big projects such as this, PJM's planning process is competitive.  That means all those transmission ideas were competing with each other to be selected.  PJM evaluated them for constructability and price, trying to find the best projects that solved the reliability problem for the cheapest price.  In order to be competitive, some companies submitted their project ideas with financial cost caps that would guarantee a final price for the project, no matter what happens in the mean time.  There are all sorts of ways to increase the price even with a cost cap, but I'm not going to get into that really complicated topic just now.

Maryland public utility BGE submitted a bunch of project ideas wrapped into a package in conjunction with other local public utilities.  None of those projects had cost caps.  While they had estimated costs attached, they are not held to the estimate.  Spend as much as you want!  One of the project ideas in this package was to rebuild  existing transmission lines from Pennsylvania to a substation named Brighton.  That project did not connect with the Doubs substation.  It looked like this:
Picture
This transmission idea wasn't just one transmission project but a series of transmission upgrades that were considered as a package.  None of these lines connected to Doubs, which feeds power to Northern Virginia.  We do not know why BGE didn't propose connecting to Doubs, and we don't really know why PJM selected PSEG's MPRP project instead.  The only clue we have is PJM's project evaluation risk matrix.
Picture
PJM decided that PSEG's MPRP was the best project in this list, and they ordered it and assigned it to PSEG.  PSEG is being held to its guarantee that it will have this project finished on time and on budget.  It is in a big ol' hurry because, for PSEG, time is money.

Once PJM selects and orders a transmission project, it's like a momma bear with a cub.  PJM will protect that transmission project and refuse to second guess itself at all costs.  The only thing that can stop PJM is a denial by the state utility commission in the state(s) where the project is located.  In that case, PJM will have to go back to the drawing board and start its planning process all over again.  Because these are competitive projects, PJM can't just pick another one.

There have only been two instances where PJM has made a change to a transmission project it ordered.  The first occurred several years ago when it was facing a denial of its planned Independence Energy Connection by the Maryland Public Service Commission.  It got that far, folks, right up until decision time!  In that instance, there was a locally-owned and operated transmission line that had recently been built that had room for another circuit (remember the planning ahead thing?).  Citizens asked why PJM had assigned a whole new transmission line on new easements to a non-local transmission company similar to PSEG when there was an existing line with open space that could hold a new circuit on the existing towers.  The Maryland PSC wanted to know also, and PJM and the transmission company fell on its sword and re-assigned that part of the project to the local utility to construct on its existing towers.  However, there were other parts to this project in Western Pennsylvania that were not changed because there was no existing transmission line with room for another circuit.  Only part of that project was changed, and the company continued trying to get approval from Pennsylvania.  Pennsylvania denied their permit and the entire project was shelved.  Turns out the years-long delay in permitting obviated the project and it was no longer needed anyhow.  The project was never built.

The second instance is happening right now.  PJM selected a transmission line connecting West Virginia coal-fired power plants with Loudoun County, Virginia's "data center alley."  A portion of this project is a greenfield line through western Loudoun on new easements.  When PJM evaluated this project, it noted that obtaining approval for new easements in Loudoun  might be a problem, so it created a "work around" on a different route, if needed.  PJM planned for this project's route in Loudoun to be rejected.  Just as PJM thought, the people in Loudoun opposed the line, and they used their money and political power to get their county government to demand PJM pull the ejector button and put the project on the alternate route.  PJM is currently considering the re-route.  However, this re-route is not exactly on "existing rights-of-way," no matter how they try to spin it.  The re-route "along existing lines" expands the existing easement and takes more property from people on the existing line using eminent domain.  The people on the re-route got mowed over by the important people in Loudoun who didn't want to have any impacts from new transmission to serve Loudoun's data centers.  They were stabbed in the back and thrown under the bus in order to save the rich people in Virginia's wine and horse country.  And they're going to remember it for a long, long time.

"Using existing rights-of-way" is not always the panacea it seems.  It's basically a NIMBY argument and pushes impacts on to others.  Even when a transmission line is rebuilt entirely on existing easements, there are still impacts from construction, as well as permanent impacts from having much higher voltage running on an easement you may be so unlucky to have on your property.  Rebuilds need new access roads for construction.  A new gravel road across your field, even temporary, will cause permanent and lasting impacts.  Just try getting all the rock out of there afterwards, or fixing the compaction that has happened.  You probably won't enjoy living with the construction traffic on it during construction either.  A rebuild on the existing easement may take out more trees along the easement, proclaiming them "danger trees" to the new transmission line.  It's a way of widening the easement without actually paying you anything.  Rebuilds aren't fun for the people who are subject to them, and horrendous for people whose home gets gobbled up by an expanded easement.

The lesson here is that moving a planned transmission line to an existing easement has only happened under certain circumstances.  The first is having space available to take a new line on existing towers.  That isn't present with MPRP.  The second was PJM having an alternate route already in mind.  That also isn't present with MPRP.

Getting PJM to change its mind and cancel MPRP entirely in favor of some other project that has not even been proposed is a very heavy lift.  So heavy, in fact, it may be nearly impossible.  PJM will have to be forced into it, and that's not going to happen quickly, easily, or inexpensively.  If you want to pursue this strategy, my advice is to hire a licensed engineer with experience and credentials working cases just like this before a regulatory commission to take a look at the PJM system and come up with an alternate plan.  Citizens don't have the right credentials to design the transmission system and PJM will just ignore them (and the PSC will ignore them as well).  You need to point to a viable plan that has been thoroughly vetted by a professional with experience designing the transmission system.  Even then, PJM will fight you on this and attack your expert.  He needs to be flameproof.  But, if you're in it for the long haul, this is your avenue, and the choice is yours.  It won't be quick.  It won't be cheap.  It won't be easy.  

Perhaps by the time you're done fighting that very long battle (with no guarantee of success) the transmission line will have obviated itself.  The data centers aren't going to wait around for a new extension cord that is mired in years of legal battle, they're going to go somewhere else with available power.

If you're going to find another solution for MPRP, make sure it's one that the entire community finds acceptable, otherwise you're playing into the NIMBY game PJM and PSEG hopes you will play.  Nobody really wins that game.  Someone alway gets stabbed in the back and tossed under the bus to save yourself.  The transmission planners and companies want you to do this because they're the ones who win... they get to have their project and someone who has to live with it is miserable.

There are plenty of transmission projects that have been cancelled entirely without anyone being thrown to the wolves because the community came together and presented a united front... we won't have this here in our community in any way, shape, or form.

​Good luck, MPRP opponents!  Carry on!
3 Comments

Digging Into MPRP

7/11/2024

2 Comments

 
Picture
Get your hip waders, folks, it's going to get deep in here!

Last night I attended the MPRP "Open House" in Brunswick.  It made the guy from Assedo pretty nervous that we wouldn't sign in and give them our information, but he said we were welcome to look around.  So, I did.  I think maybe he changed his mind later when he spied us chatting with the reporter from Fox because he found it so intriguing he needed to document it with photographs.  I saw you, dude.  Somehow, I don't think PSEG is going to be using those photos for public relations purposes.

MPRP's "Open House" was right out of the utility playbook.  Free food and beverage, free tchotchkes, and plenty of free propaganda from subject matter "experts" that sometimes couldn't stay within their specialties.  Most of them were very nice, heck, they're just doing a job.  A couple were quite snotty when they realized I knew they were blowing smoke.  And I got so far under the PJM guy's skin that he started "m'am"-ing me.  The sickest part of these open house meetings to me is always the Indoctrination Station for the kiddos.
Picture
Don't leave your kids here coloring propaganda under the watchful eye of strangers.

The first stop was the table with the PJM guy.  Stu Widom had lots of helpful information, but didn't know much about the actual planning process, and it showed.  Got himself all tweaked when I mentioned the precedent PJM has recently set by changing the route of a different project so it doesn't affect wealthy and politically connected people in Virginia's wine and horse country.  Why don't you ask Stu about that tonight?  He likes to pretend that it was for "environmental reasons" but it was nothing of the sort!  The new route crosses the C&O Canal NHP TWICE.  Environmental my foot.  Of course, poking the rich and powerful might affect Stu's own personal environment as one of PJM's political schmoozers, so maybe that's what he meant?  He obviously wasn't there to talk with citizens, but to use his bee smoker on any angry legislators or government officials who showed up.

Next I talked to one of the land agent ladies, who pretended that's not what she was.  I asked her when they were going to release the land agents on the citizens impacted by this project and she acted all confused.  I asked her if land agents would be calling on people BEFORE or AFTER the Maryland Public Service Commission approves this project.  She assured me land agents would only contact you AFTER the MD PSC approves.  We both knew she was full of it, and my investigation of regulatory filings this morning confirms
The Project is a greenfield project for most of the project route, which poses uncertainty and risk. With an in-service date of June 1, 2027, the Project faces an aggressive timeline to execute and complete all construction activities. The Project must manage ROW permitting and land acquisition risks associated with the greenfield line routes in a compressed period of time. For instance, PSEG RT will need to obtain ROWs, rights-of-entry, easements, and temporary access agreements, and in these efforts, may encounter local opposition from landowners. 
Busted!  Those land agents will be on your doorstep as soon as the routing is completed in September.

Next was one of the routing guys who told me this project was needed to supply electricity to the local area.  I told him he was wrong, then he admitted that he wasn't the subject matter expert on that.  He suggested I go over to Stu's table to find the answer to that question.  I said I'd already been there and maybe HE should go talk to Stu.  He refused, so I suggested that he not lie to people about that anymore,

I talked with a delightful young lady at the structure/electrical engineering poster.  She showed me the selected H-frame structures and told me the poles were 40 feet apart and that it would be possible to drive farm equipment between them.  I asked her what happens if someone tried that and accidentally clipped one of the poles and it fell over.  Who would be liable?  She didn't know.  I didn't suggest that she volunteer for a farm machinery rodeo, where the power company person stands in a field with their arms outstretched and pretends to be a transmission tower while farmers see how close they can drive their gigantic pieces of equipment to the "tower" without knocking it over.

I talked with another routing lady who confirmed that paralleling existing transmission lines can actually be MORE destructive than cutting new greenfield lines.  We talked about how homes and other structures are often sited right outside transmission rights of way that have existed for decades.  Paralleling that corridor with a new 150-ft wide easement would destroy everything adjacent to the existing corridor.  She said MPRP would go around homes rather than over or through them, but had to minimize how many times its line crossed the existing line.  There was also a problem where a home stood on either side of the existing easement, preventing expansion on either side.  She didn't know what MPRP would do in that instance.  One of those homes would have to be sacrificed, that's what.  Whichever side of the existing easement has more homes wins.  However, when MPRP uses new easements, it can go around any home or other obstruction and won't have to destroy anyone's home.

And finally, I talked with PSEG's staff lawyer, who happened to be sitting at Stu's table.
Picture
Very nice person who pretty much told the truth and had the answers to my rather unique questions.  She admitted that perhaps some of the other "experts" at the meeting may be making crap up and she had asked them not to do that.  I grilled her on PSEG's federal regulatory filings and cost recovery system.  This morning I found the documents and they mostly confirmed what she told me. 

​PSEG has applied at the Federal Energy Regulatory Commission to be granted three transmission incentives.  The first is the Abandoned Plant Incentive.  If granted, PSEG would be able to recover all its prudent expenditures on MPRP in the event that it is abandoned before being built through no fault of PSEG.  This would include if cannot get the permits it needs, or if PJM's need for the project changes.  The second is to set a preliminary debt/equity ratio of 55/45%.  This isn't anything to get concerned about.  The third incentive is recovery of PSEG's expenses related to this project once the project has an approved formula rate.  PSEG's initial expenditures will be recovered over a 5-year period once it has a recovery method.  This means that all the money PSEG has spent preparing this project for PJM, ushering it through PJM's competitive process, it's legal costs to make those FERC filings, the cost of all its contractors (routing, engineering, land acquisition, public relations), the food, the coloring books, even those cute little hardhat flashlight keychains (be sure to get one!).  Everything PSEG has already spent will end up added to ratepayer bills once it has its formula rate established.  The one made up fib the lawyer told was that PSEG was paying for all the current costs of the project out of the goodness of their hearts.  I hope she knew as well as I did that those costs were being put in an account as a regulatory asset that would be recovered (with interest) at a later date.

First, PSEG is waiting for FERC to approve its incentives.  Afterwards, PSEG will file for approval of its formula rate and rate of return.  Bet your eyes glazed over just then, right?  Stick with me here...  A formula rate is a set of tables that calculate a yearly rate based on numbers that the transmission company plugs in from their ledger.  As things are paid for, the costs get added to certain accounts, and the account totals get transferred to the formula rate on a yearly basis.  The number that comes out the end of the formula is the amount that electric consumers pay for the transmission project on a yearly basis.  A rate of return is how much interest the company earns on its capital expenses.  That includes physical assets, like transmission lines, land they sit on, and it also includes the cost of building them in the first place.  It's heady stuff, but anyone with a little accounting experience can handle it just fine.

Once the formula rate and rate of return is set by FERC, you can help PSEG look over its costs every year to make sure they don't include any costs in their formula rate that shouldn't be charged to ratepayers.

To wrap up... I urge you to download and read PSEG's application for FERC incentives.  It may answer a bunch of the questions I have seen swirling around, such as where's the data proving need?  Why was this project selected instead of upgrading existing lines?  If you have questions, why not take them to the PSEG attorney at tonight's meeting?  She's fun to talk to.  Be nice. 

Another utility "dog and pony show" in the books.  Don't expect to accomplish much.  MPRP isn't going to be stopped at any of these meetings, but attending is your first step.  It's simply a networking opportunity.  Come hungry.  As one landowner remarked at one of these shows years ago... "We might as well eat.  It might be all we get."
Picture
2 Comments

FirstEnergy Files For Incentives For MARL, Delays Project

7/3/2024

0 Comments

 
Picture
The MidAtlantic Resiliency Link, or MARL, transmission project has been assigned by PJM Interconnection to two different transmission builders.  NextEra is assigned to build the majority of it, but FirstEnergy ended up with the portion that runs through Frederick County, VA and Jefferson County, WV.

Long ago, even before PJM ordered MARL, NextEra filed an application for transmission incentives with the Federal Energy Regulatory Commission.  FERC approved them back in January.  Nobody bothered to get involved and comment or protest.

Everyone's been treading water, waiting to get more information, but neither NextEra or FirstEnergy has held public meetings to share information with impacted communities.  Seems like nobody is in a hurry at all.

Remember that when PJM ordered MARL, it said the project was needed to be operating by June 1, 2027 or else there would be darkness.

Back in May, FirstEnergy finally got around to requesting transmission incentives for its portion of the MARL.  It asked FERC to grant it the abandoned plant incentive.  Grant of the abandoned plant incentive begins the tally of project costs that can be recovered if the project is abandoned (cancelled) before being built.  Anything FirstEnergy spends before receiving this incentive is only eligible to be recovered at 50%.  That would mean that FirstEnergy could only collect half of the money it spends on MARL in the case of abandonment.  The other half would come out of FirstEnergy's pocket.  Fitting, don't you think, since FirstEnergy insisted on being assigned this portion that rebuilds and expands lines FirstEnergy already owns?  However, that's not what FirstEnergy asked FERC for... it asked FERC to allow it to recover 100% of whatever it has spent (plus interest) if the project is abandoned.

FERC Commissioner Mark Christie is at war against certain transmission incentives.  FERC opened a rulemaking to examine and revise its incentives more than 4 years ago, but has punted it to the side without action, allowing the overly generous incentives to continue.  
​
I'm taking this opportunity to object to FirstEnergy's request for the abandoned plant incentive.  Do they really need it, since they were so eager to have this project that they engineered some secret deal behind the scenes at PJM?  

NextEra's cost cap for MARL (as crappy as it is) did not transfer to FirstEnergy when it took over this section of the project.  FirstEnergy can and will spend however much it wants... currently estimated at $341M for a very short "rebuild" segment.  How much will they actually spend, and how soon will they spend it?  How much spending is planned *before* state approvals, which if denied can cause abandonment?  FERC should place a limit on running up the spending before project approval.

These are the comments I submitted to FERC.
er2401998.pdf
File Size: 112 kb
File Type: pdf
Download File

And here's the worst part!  As part of their filing, FirstEnergy included a copy of its acceptance letter of PJM's designation of a portion of the MARL.  In their acceptance, FirstEnergy has changed the in-service dates for its portion of the MARL.  The Virginia portions (both in Frederick and Loudoun counties) are supposed to be in-service by June 1, 2028, delayed a year from the date PJM said they were needed.  The in-service date for the West Virginia portion in Jefferson County is delayed until June 1, 2030.  That's right... 2030!  MARL is not planned to be completed and transmitting energy until 2030!  That's six years from now!  Are Virginia's data centers going to hang around waiting to build and be connected to the electric grid for another 6 years?

NO!  They won't wait.  They will go somewhere else where they can build a data center and get electric service before 2030.  The bottom may be about to fall out of Virginia's data center craze.

​Here's what FirstEnergy's acceptance letter looks like:
potomac_edison_designated_entity_acceptance_letter.pdf
File Size: 339 kb
File Type: pdf
Download File

Once the in-service date for PJM's transmission projects starts slipping, it often keeps slipping... right off into oblivion.  It can be delayed if expected load doesn't show up (but goes elsewhere). It can be delayed if the utilities run into permitting problems, such as taking a state denial in a NIETC to FERC for permitting.  It can be delayed if the utilities have difficulty procuring project components; there is a huge supply chain issue for transmission components right now.  It can be delayed if there are issues with land acquisition.  It can (and will) be delayed even further.  And, as I said in my comments...
MARL’s in-service date is already slipping. Why is that relevant? Because the electric grid abhors a vacuum. When a planned transmission (or generation) project fails to come online when needed, other projects will take its place. That’s exactly what happened with the PATH project, and what is likely to happen with the MARL project, including the Potomac Edison portion that is the subject of this filing. 
Giving these transmission companies the greenlight to spend as much of our money as they want before they finally abandon MARL many years in the future is not just and reasonable.
This transmission project may never happen, but PJM and the utilities involved feel they should pursue it anyhow. Is that because there are no other options? Or is it because there’s no harm done to them if it fails. All the burden of failure falls on ratepayers, and this encourages the utilities to take more of a chance than they would it they had some skin in the game. Utilities shoulder no risk, while collecting all the rewards. 
​

Consumers have zero control over the project’s risk factors, but they are the ones left holding the bag when it fails. As consumers, we simply cannot afford to continue to financially cover the failures of grid planners and transmission developers simply because we are the one entity without a voice in incentive awards. 
FirstEnergy has asked FERC to approve its incentive request before July 15.  Once consumers have thus insured the reimbursement of FirstEnergy's project spending, then maybe FirstEnergy can actually start working on MARL.

But what happens if FERC doesn't grant this incentive?  Will FirstEnergy still want to build its part of the MARL?  Or will it have to go back to PJM for revision?

​Stay tuned...
0 Comments

Maryland Energy Security

7/3/2024

0 Comments

 
by Patti Hankins, Harford County Maryland ratepayer
Picture
Pennsylvania State Senator Gene Yaw wrote to the PJM Board of Managers on June 14, 2024 in response to a letter the PJM BOM received from the Governors of Illinois, New Jersey, Maryland and Pennsylvania  regarding FERC Order No. 1920.  Senator Yaw is the Chair of the PA Senate Environmental, Resources and Energy Committee. Senator Yaw states in his letter:
"We must recognize that many of the challenges we face today which are accelerating very quickly — namely concerns over sufficient transmission capacity, loss of electric power generation and the inability to site and build new baseload-power generation — are tied directly to poorly-thought out state public policies which have prioritized political considerations above the needs of consumers.
For example, while many states surrounding Pennsylvania have touted their climate goals and reductions, they have conveniently ignored that they have achieved many of these goals simply by shutting down their in-state generation. As a result, they rely on imports of electricity from states like Pennsylvania, which is the largest electricity exporting state in the nation, increasing transmission costs, line loss due to distant transport of electricity and increased risk of blackouts or brownouts."

"Other state policies have upset the balance of competitive power generation by subsidizing

preferred energy resources — many of these resources incapable of providing baseload power generation on demand — or threatening coal and natural gas generation with onerous carbon taxes.
For example, just the prospect of Pennsylvania entering the Regional Greenhouse Gas Initiative (RGGI) has cost the commonwealth billions of dollars in private capital investment and thousands of jobs, and at the same time failed to demonstrate any commensurate environmental benefit to the public. Too often energy policy is being hijacked to serve politically expedient objectives rather than to meet the most fundamental objective that it should serve: ensuring the lights go on when
we flip the switch."
Maryland's energy public policy and efforts by the Sierra Club of MD have threatened the energy security of Maryland consumers. The forced closure of the Brandon Shores Power Plant by the Sierra Club has resulted in an emergency transmission project to send electricity from PA to MD via Harford County. Over 1 million BGE customers have been placed at risk for having reliable electricity for their basic needs. Maryland's energy policy focuses on wind and solar generation. Both are intermittent energy sources that are completely dependent on Mother Nature. Our Maryland Governor and progressive leaders in the House of Delegates and Senate are just fine with shutting down baseload-power generators in our State. Where do they think the power is going to come from? BGE touts the Brandon Shores Retirement Mitigation Project as "Good Energy at Work" with a website named "good energy in progress".

So baseload-power generation, namely coal, natural gas and nuclear are good if they come from Pennsylvania but bad when it's home grown in Maryland? How many Pennsylvania extension cords are going to be needed to keep the electricity on in Maryland? We know that the PJM 2022 Window 3 projects will bring another extension cord from the Peach Bottom Nuclear Plant's substations to be colocated with the Brandon Shores "good energy" project. And another extension cord from Chanceford Township in York County, PA to Frederick County via Northern Baltimore County and Carroll County. And yet another extension cord from Hunterstown, PA to Carroll County. What happens when Pennsylvania runs out of power generation to send?


Pennsylvania is now starting to see data centers and Bitcoin mining companies locating near generators in the State. In March, Amazon Web Services purchased a 1,200 acre data center campus adjacent to the Susquehanna Steam Electric Nuclear Station. This acquisition allows AMS to purchase energy directly from the Station.

And just this month Bitfarm, a Bitcoin mining company announced it would locate in Sharon, PA where it would have access to an abundant energy supply. Bitcoin mining like data centers uses massive amounts of power. 

Maryland has become much too dependent upon Pennsylvania for its electricity generation. I ask each Maryland state legislator, what steps will you take to secure Maryland's energy supply before it's too late?
0 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.