StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

FirstEnergy Transmission Open House

6/5/2025

1 Comment

 
Picture
Ever feel like the filling in a tuna sandwich?  The "stuff" inside an Oreo?  Well, that's exactly what you are if you're on the Jefferson County section of PJM's 502 Junction to Goose Creek transmission project.  We're being sandwiched between NextEra's MARL on the western side, and FirstEnergy's Gore-Doubs-Goose Creek project on the eastern side.  We're the one remaining area without any maps or information.  Apparently we're being saved for last because we're the ones FirstEnergy is most worried about.  We're the ones who are supposed to remain compliant and in the dark because FirstEnergy has not given us any notice.  Well, wake up folks, this is your notice!
Picture
FirstEnergy has finally emerged from their bat cave to disseminate public information about the eastern half of the project.  As I told you several weeks ago, FirstEnergy is calling the eastern half of MARL the melodious Gore-Doubs-Goose Creek project.  You can continue to call it MARL if you like.  It doesn't matter what you call it, as long as you don't call it late for the financial incentives buffet (haw, haw, haw).

But, FirstEnergy is only willing to share information about the Maryland part of its project, and says it wants to file an application with the Maryland PSC by the end of the year.

Despite PJM's empty promises about "using existing rights of way" for eastern MARL, FirstEnergy is planning to expand existing easements and acquire more property.
While the project is mainly using existing rights-of-way, there are “some limited areas” where the rights-of-way will have to be expanded to accommodate new transmission structures, according to the fact sheet.
Fact sheet?  What fact sheet?  Maybe it's on their website?  What website?  The only information you're going to get is going to be in person at the ONE and ONLY "Open House" FirstEnergy is holding for this project.

A public information session on the project is scheduled for June 11 from 6 to 8 p.m. at the Upper Montgomery County Volunteer Fire Department in Beallsville.


This is your only chance to get information.  Be there.

Meanwhile FirstEnergy continues to slink around, approaching landowners with predatory proposals before giving them complete information about the project.
Potomac Edison has “approached a handful of property owners in those areas (a mix of commercial or privately owned, undeveloped land) to discuss obtaining those easements for fair market compensation.”

Right now, Potomac Edison is conducting “preconstruction activities” along the transmission rights-of-way, according to the project fact sheet.
​
Company employees might be seen driving or walking the properties where the rights-of-way are, taking measurements, placing boundary flags, and gathering soil or vegetation samples.
Don't just sit there.  Do something!
1 Comment

West Virginians Could Pay More than $440M for New Transmission Lines

5/30/2025

0 Comments

 
Picture
A new study released May 29 found that West Virginia electric consumers will pay hundreds of millions of dollars for new transmission lines ordered by regional grid operator PJM Interconnection to export power produced in West Virginia to new data centers in Northern Virginia. The study was performed by Cathy Kunkel, an energy consultant with the Institute for Energy Economics and Financial Analysis (IEEFA).

The study focuses on the proposed 500kV MidAtlantic Resiliency Link and the 765kV Valley Link transmission projects that are planned by PJM to cross Jefferson County, but have not yet been permitted or constructed. If approved by the West Virginia Public Service Commission, the projects will increase electric bills in the state by more than $440M, according to IEEFA.

"The possibility that West Virginia ratepayers will be paying over $440 million to subsidize Virginia's insane energy policies highlights the ludicrous nature of our regional energy transmission system. Mountaineers should not pay for Virginia's decision to eliminate their coal and natural gas plants. West Virginia needs to keep our energy to build our economy, not Virginia's. If Virginia wants to change it's policies and buy coal and natural gas, we'd be happy to sell them as much as they can afford. Our beautiful state should not see ugly transmission lines forced upon us to power Virginia data centers”, said West Virginia Delegate Bill Ridenour, R–Jefferson, after reviewing the study.

The transmission lines were proposed as a fix for rapidly growing electricity demand for new data centers in Northern Virginia, according to local transmission expert Keryn Newman, who likened the new lines to enormous electric extension cords for the data centers that don’t provide any benefit to West Virginians and instead scar our landscape, take our property, and send us the bill.

“New transmission lines crossing West Virginia to export our electricity to data centers in Virginia are going to cost West Virginians at least $440M in increased electric bills at a time when they can least afford it. We need to keep our electricity here, working to empower West Virginia’s economy and its citizens. We can’t afford these new transmission extension cords,” said Newman.

Mary Gee, a resident of Summit Point whose land and home may be taken to make way for the new transmission lines is troubled by the IEEFA report. 

“It’s bad enough that my family may lose our home of 20 years, but to be forced to pay for that destruction through higher electric bills is salt in the wound,” she said.

More information about the IEEFA Study. 

0 Comments

Checking NextEra's Math

5/22/2025

0 Comments

 
Picture
NextEra Energy Transmission MidAtlantic, designated entity for the MidAtlantic Resiliency Link, or MARL, project recently announced its Actual Net Revenue Requirement and Annual True-up Meeting.  The meeting will be held on June 12 at 3:30 p.m. and probably won't last more than an hour (depending on how many questions you ask).   Interested parties can attend via Webex or telephone.  NextEra requests that you répondez s'il vous plaît, but it's not required.  See meeting notice linked above.

An interested party is defined in NextEra's Formula Rate Protocols (PJM OATT Attachment H-33-A). 
"For purposes of these protocols, the term Interested Party includes, but is not limited to, customers under the PJM Tariff, state utility regulatory commissions, consumer advocacy agencies, and state attorneys general."  If you pay an electric bill in the PJM region, NextEra's transmission costs are flowing through into your bill and therefore you are an interested party by definition.  This issue has been litigated before FERC many times and FERC has emphatically found every time that consumers are interested parties.

At the meeting, NextEra will be presenting its Formula Rate Update to true up its estimated 2024 revenue requirement with its actual expenditures.  It will also be presenting its estimate of its revenue requirement for 2025. 

What's a revenue requirement?  It's the total amount NextEra gets to collect from ratepayers in the PJM region for each year.  Once NextEra calculates its revenue requirement, PJM collects that amount from responsible load serving entities (LSE -- the company that actually sends you your bill).  The LSE in turn collects the transmission rate from you in your bill.  This is how the costs of new transmission get included in your monthly electric bill.

NextEra will NOT be discussing or entertaining any questions about its transmission projects.  This meeting is ONLY about NextEra's transmission formula rates.

What's a formula rate?  It's a series of mathematical calculations into which the utility plugs certain numbers.  It calculates the utility's annual revenue requirement.  Formula rates take the place of a stated rate, which is a set dollar amount that the utility would collect from its customers.  Instead of a set number, the regulator sets a formula for calculating yearly rates so that there doesn't need to be a full blown rate case every year.  The formula is the rate, not a fixed number.  The revenue requirement can therefore fluctuate from year to year.

Now take a deep breath.  

This is NextEra's formula rate, populated with numbers from 2024.

It's not as hard as it looks.  Each calculation names where the numbers it plugs in come from.  The numbers used come from NextEra's FERC Form No. 1.

The Form No. 1 is an accounting of NextEra Energy Transmission MidAtlantic's finances for 2024 that is organized into various accounts.  If you've ever worked in accounting, or taken an accounting course, you know that an entity's finances are organized into certain accounts that describe each general class of expense.  The list of descriptive accounts for an entity is called its Chart of Accounts.  All utilities regulated by the Federal Energy Regulatory Commission use FERC's Chart of Accounts, called the Uniform System of Accounts (USofA).  Each account listed on the Form No. 1 (and transferred to the formula rate) has a description and rules for its use.  Not every account in the USofA gets transferred to the formula rate template.  Only certain accounts are included in the formula rate.  Other accounts are not included in the rate.  For instance, FERC Account Number 426.4, Expenditures for certain civic, political and related activities, is not included in a formula rate.  That's because those kinds of expenses are not recoverable from ratepayers under FERC's accounting rules.  A utility that chooses to make those kind of expenditures pays for them out of its own funds. 
When a utility does not follow the descriptions and rules, this can happen.

Sometimes, utility accountants accidentally record expenses in an incorrect account.  Not a problem if both accounts are either recoverable or non-recoverable.  However if a non-recoverable expense is accidentally recorded in a recoverable account, it would get transferred to the formula rate and recovered from ratepayers in error.  In that case, the utility must refund that expense to ratepayers.

NextEra will also be discussing its projections for 2025.  These numbers are based on historic averages or company budgets.  The estimated revenue requirement is what will be recovered from ratepayers in 2025.  However, it is just an estimate.  This estimate will be compared with actual 2025 expenses in 2026 (called a true-up) and any overage will be refunded, or any under collection will be wrapped into the next year's rate.  This way, the utility only collects its actual expenditures from ratepayers.

As an interested party, you will be able to ask about specific numbers that are plugged into the formula rate, the accounts included in that line item, and how the actual expenses were classified for accounting purposes.  If the utility cannot provide detailed answers during the meeting, there is a process for interested parties to submit information requests to seek more details about the expenses and/or calculations to make sure that the rate was calculated correctly.  If you are not satisfied with the answer you receive to your question, feel free to ask them how to submit additional written information requests.

Yes, this is heady stuff, but it can be mastered by regular people.  Having an accounting background helps.

You might wonder why this process exists.  Doesn't FERC check NextEra's math when they file their annual revenue requirement?  The answer is NO.  No, they do not.  FERC relies on the entities that pay these rates to examine and question them.  Occasionally FERC may audit some of these utilities, but that's a random process that never looks at every one filed.  Because the formula rate has been determined to be just and reasonable, FERC assumes that the utility that uses it follows all the rules when it fills out the rate template every year.  Therefore, FERC doesn't need to even look at the filings.  They leave that job to you.  You might think that your LSE or your state regulator or other state office reviews these filings for accuracy.  NO.  No, they do not.  Your electric company just pays the bill to PJM and passes these costs on to you.  It doesn't care how much they are.  Your state offices usually don't have the skills or resources to review formula rate filings.  In a lot of cases, they don't understand them at all.  That leaves it up to you...

So, if you want to plunge into NextEra Energy Transmission MidAtlantic's annual transmission revenue requirement to check their math, don't miss the meeting.  It's your first step.
0 Comments

West Virginia Public Service Commission Passes the Buck

5/14/2025

0 Comments

 
Picture
The West Virginia Public Service Commission's mission statement is:
The purpose of the Public Service Commission is to ensure fair and prompt regulation of public utilities; to provide for adequate, economical and reliable utility services throughout the state; and to appraise and balance the interests of current and future utility service customers with the general interest of the state's economy and the interests of the utilities.
However, when a customer filed a general comment with the PSC recently regarding the way FirstEnergy is shirking its duty to provide public information, this is the response she got:
Thank you for contacting the Public Service Commission of West Virginia regarding the transmission line project. We are aware of plans for the proposed transmission line, but have not yet received a filing in this matter. We expect the developer to apply to the PSC for a certificate of convenience and necessity (under code section 24-2-11a) before beginning any construction. Once the PSC receives the application, there will be a public notice (the law requires newspaper publication in counties where the line is proposed to be located) and an opportunity for the public to comment and to file protests and to ask for the PSC to hold a hearing. We encourage you to share your comments once a case has been opened and is available for public input.
The consumer corrected the PSC with this response:
​This section of state code that got amended back in 2010.  It is WV Code §24-2-11a(c) available at this link:  

https://code.wvlegislature.gov/24-2-11A/


It says:  At least thirty business days before the deadline set by the Public Service Commission to file a petition to intervene with regard to the application, the applicant shall serve notice by certified mail to all owners of surface real estate that lie within the preferred corridor of the proposed transmission line. Notice received by a named owner who is the recipient of record of the most recent tax bill that has been issued by the county sheriff's office for a parcel of land at the time of the filing of the application is sufficient notice regarding that parcel for purposes of this subsection.

I have the right to intervene as an impacted citizen. I also have a right to intervene and participate in the case, not just file a comment.
And then the PSC's Director of Communications responded by passing the buck and telling the consumer to go away.
You do have a right, as any citizen does, to ask to intervene in any case before the Commission.
However, in this case, there is no case before the Commission, so therefore we cannot take or act upon your request.
Until the company files a petition seeking our approval of the line, there is no case. That has not been filed by the company.
If such a request is filed, we will be happy to notify you and then you can petition to intervene.
In the meantime, I may suggest you file your protest with the company.
I hope this helps. Please feel free to call me at any time if I can be of assistance.
Aren't there any lawyers at the PSC that can acknowledge that the company has an obligation to notify impacted landowners via certified mail once an application is filed?  That's what the customer was looking for.  She filed a general comment seeking help with the fact that FirstEnergy is approaching landowners to seek Right of Entry on their properties without providing any information about their project.  FirstEnergy has provided no information whatsoever about their project to the impacted communities.  Do impacted landowners have to wait until an application is filed to get basic information about the project and what it intends to do to private property?

Furthermore, a different segment of the same transmission project has absolutely failed to provide effective engagement with other impacted landowners.  NextEra has been holding "Open House" meetings in West Virginia that leave landowners confused and angry.  The meeting setup is loud and confusing.  The maps are not labeled.  The comment cards cannot be filled out later and mailed in.  Attendees cannot have normal conversation with project representatives because they cannot hear what they are saying and answers are non-responsive or misleading.  The company's website is devoid of meaningful explanation or information about this project.

The 500kV MARL project is failing at public engagement on all fronts.

But yet when consumers go to the officials who are supposed to protect them from predatory and outrageous behavior by the public utilities it regulates, they get told their comments cannot be accepted.

In the case of FirstEnergy, impacted landowners and consumers do not even have a contact for the company in order to "file your protest with the company."  Landowners are being preyed upon and nobody is stepping up to protect them.

Keep filing your general comments with the WV PSC, even though they claim they cannot accept them.  And keep a record of your correspondence.  Please forward any refusal of the PSC to accept your comment to your state delegates and senators and ask for their help.    These public servants work for us!

To file a general comment with the WV PSC, go to this link and fill out the form.  Maybe if they receive enough comments about the outrageous behavior of regulated public utilities they will have to do something?

Landowners are not just asking to intervene before an application is filed.  They are commenting on the current process before the application is filed.  Communities deserve an open and transparent process leading up to the filing of an application and they deserve to have their right to information protected by the Public Service Commission.  After all, that is the PSC's mission!

Keep filing your comments with the PSC regarding your concerns with public engagement (or lack thereof).  The PSC has rules that must be followed.  The least it can do is accept and acknowledge your comments about these major transmission projects that have been proposed to cross our state.  Let them know what you think about what's happening now, even if an application has not yet been filed.  Don't let them pass the buck!
0 Comments

Letting the Cat Out of the Bag

5/12/2025

0 Comments

 
Picture
An out-of-state utility company hoping to build the MidAtlantic Resiliency Link, or MARL, has been telling local elected officials that its project will bring millions of dollars of new tax revenue to county coffers.

But, will it really?  Or is this just a pig in a poke?
A pig in a poke is a thing that is bought without first being inspected, and thus of unknown authenticity or quality. The idiom is attested in 1555:

I wyll neuer bye the pyg in the poke
Thers many a foule pyg in a feyre cloke

I will never buy the pig in the poke
There's many a foul pig in a fair cloak

A "poke" is a sack, so the image is of a concealed item being sold.
​
Starting in the 19th century, this idiom was explained as a confidence trick where a farmer would substitute a cat for a suckling pig when bringing it to market. When the buyer discovered the deception, he was said to "let the cat out of the bag", that is, to learn of something unfortunate prematurely, hence the expression "letting the cat out of the bag", meaning to reveal that which is secret.
Has anyone bothered to ask the company to show you their math and verify that it actually agrees with the utility tax scheme of your state?  I don't think anyone has.  I've heard that when details are sought, the subject gets changed, or when pressed they say we will find out the details during the state PSC case.  That's magic math, according to one of my elementary school teachers -- where the answer appears out of thin air without showing your work to calculate it.

How ARE utility taxes assessed and paid?  If you don't know, it's time to find out.  There's a whole lot of confusion and nobody at the local county level seems to know.  Don't take some out-of-state company's word about how your own tax system works.  Here's the skinny on how it works in West Virginia...
Although most real and personal property is assessed at the local level by county assessors with county commissions approving the final rates, the Board of Public Works approves the real and personal property values of public utilities whose properties stretch across two or more counties. Rather than have each of the 55 assessors determine the value, the property is appraised and assessed by the Tax Division.
Utility property taxes are not handled by local government.  It's handled by a state office.  Counties have no authority over the rate or the collection of these taxes.  Once the state has assessed these utility taxes, the utilities appeal and negotiate these rates to have the tax lowered.  Once a deal is reached, the state tax office apportions the utility tax it has collected like this:

 "...the value of the property therein of every such owner or operator as valued or assessed hereunder and the relative value of such operating property within each county compared to the value of the total operating property within the state, to be determined upon such factors as the Auditor shall deem proper;".

Bottom line?  Counties have no control over utility taxes on transmission lines and the tax rates can fluctuate.  Counties only get a small portion of what is collected.  Go ahead, check with your county clerk to find out how much utility tax revenue your county received last year, and then figure out how much of that was actually due to electric transmission lines that cross your county.  Maybe you can buy a cup of coffee with it?

So, where did the company get  the numbers it is using to entice local support?  Did they sit down with the West Virginia Board of Public Works and the state tax commissioner and negotiate a deal?  Did they calculate how the value of the utility property will depreciate over the years until it's nothing but salvage?  Did they mention that transmission utilities don't buy real estate, they simply take an easement and the landowner continues paying taxes on his property, including the easement?

I doubt it.


Corporations are old hands at manipulating local governments to believe that there's a pig in their poke, and not a mangy alley cat, when the corporation is selling new development projects to us "locals."  And so they have developed a computer program to help them out that would make P.T. Barnum proud.  But, instead of calling it something fitting like "Circus Sideshow Software" its name is IMPLAN.  IMPLAN calculates job numbers, taxes, and other economic development numbers that excite local elected officials based on the capital costs of a proposed project.  If the utility company isn't using IMPLAN to come up with these pie-in-the-sky tax revenue numbers, it's using another very similar software company.

And you know what they say about computers -- garbage in, garbage out!

Economic factors calculated by a computer algorithm are not realistic.  You'd get more tax revenue and jobs out of a new fast food restaurant than you'd get from a new transmission line passing through your county and delivering nothing of value on its way.

Job predictions are extremely inflated.  I have seen transmission full-time jobs predicted over the long term that don't even make sense!  Building high-voltage transmission is a highly specialized skill.  Contractors from other states hired to do the actual build will import their own workers for the duration of the job in your community.  IMPLAN and its computerized cousins calculate all the economic impact that such transient workers will cause and then try to sell it to local elected officials as a "benefit."  Hotel rooms, fast food, and gas for their vehicles for the month or so they're onsite isn't really going to make a difference on a local level.  In addition, IMPLAN will spit out some number of full-time, permanent jobs created in your community by the project.  I'm sorry, but this just doesn't happen.
Picture
Local transmission workers discuss where to place their ladder so they can climb up and squeeze electricity through the new transmission lines in your community.
Once the line is built, there are no local jobs associated with it.  Operation and maintenance of the line is handled by remote teams.

But, back to those tax revenue claims...

Ask the company how it has balanced the actual reduction in local tax revenue caused by the project  with the fictional number spit out by IMPLAN.  It hasn't done that at all.

New transmission lines across your county are going to devalue the real estate in your tax base.  A property crossed by a transmission line loses value and the owner of that parcel can appeal his assessment because of the devaluation the transmission line has caused.  In addition, the transmission line can impact many planned developments and future land uses.  What development is currently going on, planned, or dreamed about by your county?  Maybe you want to lay that out on a map to see how close it is to the proposed transmission line route?  New subdivisions, business parks, commercial developments, or maybe just some community improvement like parks, schools, or community services, can all be impeded, or cancelled altogether, if the new transmission line interferes with the proposed development.  Whittled down to its most basic level, it's going to harm local landowners and investors who planned to monetize their land in the future, whether it's for retirement or simple profit.  New transmission lines cause a decrease in your county's current tax base and any future prospects that might increase it.

Also consider that the transmission company actually pays no taxes at all on the transmission lines it builds... you pay those taxes!  A utility collects its cost of service from ratepayers (plus regulated profit).  Everything the company spends on its transmission lines, including real estate, personal property, business and income taxes, is reimbursed to them by electric ratepayers as the expense is incurred.  All persons in your county who pay an electric bill (including the county itself) are paying those taxes!

Think about that while you're comparing the transmission company's bulging poke with reality.  The cat's out of the bag!
0 Comments

Landowners Come Last

3/1/2025

0 Comments

 
Transmission companies use the same playbook every time.  By now, I know it by heart.

Projects are planned by the regional grid operator that many people don't even know exists.  Although the process is open to "stakeholders," those stakeholders have no idea that such an organization is planning a new transmission project that is going to cross their land and, perhaps, take their home.  Once approved by the grid operator, the utilities conduct secret meetings and grease the right palms.  They engage with your state agencies and elected officials to convince them that the project is a good idea.  It's all one big, happy party... SECRET happy party.  Your elected officials and your state agencies don't engage you or send notice.  They leave that up to the utility, and the utility doesn't want you to know until it's so far into the routing process that you can't have any real impact on where it goes.  You're supposed to remain dumb and happy until the last minute.  Then the utility springs it on you as a fait accompli and conducts a farcical public information and notification process.  At this point, they hope you're out of options and that you will jump into action to push the project off yourself and onto your neighbor.  That's the first reaction of the vast majority of people, until someone finally figures out it's not about where it goes, it's about whether it goes.

But, until you finally receive notice, you should know that the utility has been very busy consulting with everyone except the landowner who would be forced to host the transmission line on his property.  And don't you know it, NextEra has been very busy trying to schmooze a path for its portion of the MidAtlantic Resiliency Link (MARL).  This presentation recently surfaced, although it's been common knowledge to a bunch of people who were hiding it from you for months.
marl_schmooze.pdf
File Size: 4634 kb
File Type: pdf
Download File

Perhaps your most important take away from this little peek into what's been going on behind your back is this slide.  Click to download the above file to see a larger version.  
Picture
This is the roadmap of NextEra's routing process.  The red box is where "we" are.  It's a point called "Engage Counties and KEY STAKEHOLDER With Preliminary Route."  Right... KEY STAKEHOLDER... but that doesn't include the most important KEY of all... the landowners who will be asked to host this project.  When are impacted landowners notified?  Three turns away at "Open Houses", which is nearly the last pit stop on this highway to hell.  By that time, everyone else that won't see it from their house has been consulted about the route and brought on board.  Landowners come last on this journey.

Landowners are presented with a couple of routing options and are expected to spend all their time fighting each other over where it goes, instead of joining forces against the real enemy.  And they call this "community consultation"... when the decision has already been made.

DAD - Decide, Announce, Defend.  DAD is a top-down, minimally participatory method of public management.  You're sheep and they are the sheepdogs.  This never works on a smart, engaged public because the last "D" never ends.  People won't give up when their very home is on the line.  And when the utilities are put on the defensive, they say and do the stupidest things, most of them dishonest.  Nobody is buying it.  We all know how to smell a rat.  Propaganda is a useless waste of money.

​So, what else is in that power point?  Well, there's a full map of the MARL project, including FirstEnergy's portion.  NextEra has been pretending that the eastern part of the project doesn't exist and that their project simply ends in Frederick County, Virginia.
Picture
But it's clearly shown on a map that the end of NextEra's MARL is simply the HANDOFF POINT.  That's where their transmission line connects directly to FirstEnergy's transmission line.
Picture
We're all in this together, folks!  Landowners and communities impacted by NextEra's MARL are in the same boat as landowners impacted by FirstEnergy's MARL.  Neither one of these line sections can happen without the other.  Kill one, kill them both.

Here's what the landowners impacted by NextEra's MARL are facing:
Picture
Landowners on FirstEnergy's portion are facing the tear down of an existing 138-kV transmission line, expansion of the existing easement at least 100 feet, and the building of a new 500kV line with a 138kV circuit on the same new towers.

Pay attention, people!  It's coming!  Although the most FirstEnergy has done is threaten to "survey" its existing easements on its part of this project, you should also know that they are working behind the scenes, much like NextEra, to schmooze KEY STAKEHOLDERS to accept the project before you even realize that they've decided on a route across your property.  The announcement will come later, with Open Houses of our own.  By that time, the route is set in stone.  Be prepared to fight!
0 Comments

Loudoun Pushes Data Center Burden Onto Neighboring States

8/21/2024

0 Comments

 
Picture
Loudoun County, Virginia, has the largest concentration of data centers in the world.  The world!  It also has the nickname "Data Center Alley."  Loudoun County has become gross with data centers, and continues building more.  The data centers are Loudoun County's cash cow, providing a third of its annual budget.  Loudoun County is also the wealthiest county in the nation.  The entire nation!  Loudoun County is home to the rich and, due to its proximity to Washington, D.C., the powerful as well.  The rich and powerful thought nothing of Loudoun destroying its eastern regions, tossing them on the altar of the data center cash cow.  After all, more data center tax revenue means less taxes for the rich and powerful in the western regions of Loudoun.  Out of sight, out of mind!  Living near nasty infrastructure was fine for the plebeians, as long as the benefits from hosting it flowed to the rich and powerful.

But then something happened... the data centers needed more resources than Loudoun County had.  Now, normal people in that situation would begin building the resources needed to feed their cash cow, but that's not how things are done in Loudoun.  Loudoun continued to build its data centers and expected the needed resources would come from neighboring states just like magic.  Except importing those resources come with consequences, like new transmission extension cords.  Perish the thought!  Transmission lines are fine for those other states that still *gasp* burn coal to create electricity to power Loudoun's data centers, but they absolutely cannot happen in Loudoun!  Loudoun is ruled by the rich and powerful, don't cha know, and they absolutely cannot be burdened with anything so ugly and gauche as an electric transmission line bringing power to their data centers.

So the rich and powerful grabbed their government servants by the scruff of their necks and demanded that the government make the bad stuff go away... or else!

The Loudoun County government and local elected officials began holding secret meetings with NextEra, other transmission companies, PJM, and Western Loudoun's Sacred Cows to find a way to push the transmission nasties out of Loudoun.  After all, aren't those other states lesser trash cans in service of the rich and powerful in Loudoun?  When other citizens who would be impacted by a transmission line re-route asked to be included in the meetings, they were purposely excluded.  And wouldn't you know it... that's exactly where the MARL transmission line ended up... on the property of the landowners who tried to be included in the secret government meetings.  Loudoun County met with and did the bidding of a handful of rich and powerful citizens to TAKE property from other citizens not as fortunate.  Pepe' Le Pew tells me that kind of discrimination stinks to high heaven!
Picture
And so the MARL transmission line got pushed out of Loudoun County and over into Frederick and Montgomery Counties Maryland.  Benefits for Loudoun, impacts for neighboring states.  

The re-route will cost everyone in PJM an additional $167M to spare the sacred cows in Loudoun.  Loudoun thought nothing of this, even though other towns who ask for transmission siting concessions are usually required to pay the difference.

I'm starting to understand why Loudoun is the wealthiest county in the U.S. -- it doesn't pay its own way.  Loudoun County takes from neighboring states like a parasitic worm.

And now here they go again, with another transmission line that Loudoun County has demanded be buried for a short section that abuts another group of Sacred Cow homes.  That's all fine and good, but the burial is going to cost an additional $423M, a project cost increase of 61%!  Between these two transmission projects, saving Loudoun will cost electric consumers in other states more than half a billion dollars!

And who pays for that?  Every last electric customer in the PJM region.  Both of these projects that disturb Loudoun's delicate sensibilities are regional reliability projects that are charged 50% to all PJM consumers based on their load share ratio, and the other 50% is charged to the "users" of the project, which spreads to neighboring states like West Virginia, Pennsylvania, and Maryland.  Virginia is only paying a portion of the cost of the new transmission extension cords to serve their data centers.  Any increase in costs will come out of the pockets of everyone in the PJM region.

So, how does Loudoun County think the burial of transmission lines near Landsdowne should be paid for?  
As for the excess cost, the County believes that a special customer class, made up of high-wattage customers, would be proper for the Commission to consider. The increase in electrical demand can be directly traced to the connection of an identifiable class of such high-wattage users to the grid. It is in the public interest for the Commission to shift the cost of undergrounding some of these lines to the high-wattage customers creating the demand for them.  
Well, that's a low-information expert for ya... Buddy Rizer doesn't know diddly about utility rates.  While Virginia *could* create a new rate class, it absolutely will not do so within this docket.  Asking for something like that is outside the bounds of this proceeding.  Therefore, Loudoun is not providing any way to pay for the excess cost.  And, even if Virginia created a new data center customer class to charge its share of the transmission extension cords to the data centers it hosts, that doesn't do a damned thing for the ratepayers in other states, who don't have any data centers (or data center classes) to charge their share of the excess cost of burying lines in Loudoun County in order to spare Loudoun any impacts.  It's another selfish suggestion on the part of Loudoun County.  And where was Loudoun County when we were arguing at FERC about whether Virginia's data centers should pick up the entire $5B cost of the Window 3 projects meant to serve them?  Nowhere.  It doesn't want to pay for the projects it has caused.  It just wants all the benefits without any of the impacts.

It's all over Buddy Rizer's testimony.  And for the rest of us who don't benefit from Loudoun's data centers, or keeping Loudoun free from invasive transmission projects, it's positively revolting!
buddy_rizer_testimony
File Size: 575 kb
File Type: buddy rizer testimony
Download File

The citizens of Loudoun County are expressing significant concern about the impact that further above-ground transmission lines will have on their community. With hundreds of miles of these lines already crisscrossing the County, citizens are hoping for a thoughtful approach to future development. Numerous comments from the community reflect a growing movement to explore alternatives to traditional transmission lines. Organizations such as the Lansdowne Conservancy, Waterford Foundation, Loudoun Transmission Line Alliance, and Piedmont Environmental Council have organized public meetings to oppose these proposals, driven by a strong desire to prevent overhead transmission lines from dominating the landscape and causing irreparable harm to historic, economic, and natural resources in Loudoun. The community opposition was key in PJM’s decision to approve an alternate route for delivery.
WHAT MEASURES CAN BE TAKEN TO PROTECT LOUDOUN COUNTY’S SCENIC ASSETS FROM THE IMPACT OF HIGH-VOLTAGE POWER LINES?
Where appropriate and feasible, undergrounding may provide a reliable and long- lasting energy transmission solution that is less prone to outages with minimal disruption to the look and feel of the community at large. This approach will preserve the landscape for current and future residents and maintain the history and beauty of the County. Additionally, it supports a reliable and sustainable path forward as Virginia works to meet its energy production and transmission goals. By placing power lines underground, impact to scenic assets can be minimized while ensuring a resilient and efficient power infrastructure.

Picture
Don't get me wrong... I don't believe anybody should be impacted by transmission lines.  And that's the difference between me and Loudoun County... Loudoun County seems to think that only its special residents should be free from the impacts of its data center extension cords.  Loudoun County is perfectly okay with impacts to landowners in West Virginia, Pennsylvania and Maryland.  Loudoun County isn't advocating for its extension cords to be buried in those other states.  Those people simply don't matter to Loudoun County, except when they pay the extra cost of keeping Loudoun transmission line free.

It's about time that Loudoun started shouldering its own data center burden.  The data center transmission problem is completely of Loudoun County's making.  It could end it in a hot minute by putting a moratorium on data centers.  It could also solve it by building some new electric generators in Loudoun near the data centers.  Why don't you do these things instead of taking from neighboring states to fill your own coffers, Loudoun County?  Solve your own problem!  Your neighbors are quite sick of your hubris.  Here's a little advice from one of your favorite people!
Picture
0 Comments

How PJM and FERC Caused Huge Spikes in Regional Power Bills and New Transmission

8/9/2024

2 Comments

 
Picture
PJM's recent capacity auction resulted in huge price spikes in the cost of supplying power to electric customers in the PJM region for the 2025-2026 year.  It was directly caused by the actions of PJM and FERC.  These entities aren't protecting ratepayers, they are harming them!  Let me explain...

PJM holds annual capacity auctions to secure the provision of electricity three years in advance.  A capacity auction is not actual electricity, it is a promise from a generator to supply a certain amount of energy at a future point in time.  This is how PJM ensures that it will have enough electricity supply available three years from the auction.  PJM is paying these generators to be available to produce energy when needed during the auction year.  PJM starts by announcing a certain amount of electricity is needed for the auction year.  Generators submit bids of how much it will cost to be standing by to produce that electricity during the auction year.  PJM stacks the bids by price, and each bid is represented by an amount of electricity and a price.  PJM then looks at its bid stack and finds the place where the capacity need is met.  Whatever the price of that bid is the clearing price for all the capacity bids lower in the stack.  Those bids that go over the capacity price are not accepted.  At the end of the auction, PJM has a stable of committed generators sure to provide the power when needed 3 years from the auction date.

PJM does not order generation.  Generation is a market construct, where generators build when the capacity prices are profitable.  If the clearing price at auction is high, it would entice the development of new generation.  If the clearing price is low, many generators may not have enough revenue to continue to operate at a profit.  This is how PJM manages generation to make sure there is always enough, but not too much.  The auction serves as an important warning bell... when clearing prices are high, it means more generation needs to be built.  The auction sends a signal to generators to build more when the prices are high.  More generators lowers prices because there is more competition in the supply.  But what happens when the prices are high at the auction and no new generators get built?  That's exactly what just happened... there is a dearth of needed generation in PJM so prices shot through the roof to record highs.

The problem here began with PJM making a proposal to change the parameters of its auction.  In order to do so, it needed FERC's permission.  A battle broke out at FERC, with many other parties objecting to the auction changes.  FERC moves at a snail's pace and can take years to make a decision on a request.  The more parties to a case, the longer it takes to resolve it.

Because of the battle going on at FERC, the auctions got put on hold.  As Power magazine says, 
BRA auctions are usually held three years in advance of the delivery year. While the 2025/2026 auction was originally scheduled to be held in May 2022, it was suspended while the Federal Energy Regulatory Commission (FERC) considered the approval of new capacity market rules. The recent July 2024 auction stems from a compressed schedule that aims to return to the three-year forward basis. According to PJM, the next BRA—for the 2026/2027 delivery year—is scheduled for December 2024.
FERC suspended PJM's capacity auctions while it resolved the issue.  That's like turning off the warning system.  PJM's annual capacity auction couldn't send the market signal to build new generation because it wasn't being held.

During this time, an extreme change in the power needs of the PJM region was underway.  Many baseload fossil fuel generators closed, either the result of the last auction's low capacity prices, or because they were "dirty" and no longer socially acceptable.  The new generation that entered the market could not keep up with the amount of generation that was closing.  As a result, we had less generation available.  Also during this time, the building of new data centers and increasing power demands for AI shot through the roof.  No new generation to supply power for these data centers was proposed or built because PJM's auction warning bell was not sounding due to the auctions being suspended.

PJM used the only tool it had available to meet regional need... transmission.  PJM conducted a competitive transmission window to connect the remaining generators with the new data center load.  Unfortunately, the majority of the available generators are located in WV and PA, and the data center load is in Northern Virginia.  PJM asked for new transmission to connect the two, and it ended up with a whole bunch of new projects, including MARL and MPRP.  PJM says they are "needed" to supply power to the data centers because no new generation has been built anywhere near the data centers.

Now that FERC has finally resolved the issue and PJM has its new market parameters, PJM recently began holding auctions again.  The first new auction for the 2025-2026 year was held just 10 months before the auction year begins, instead of 3 years in advance.  There's no way new generators can be built in 10 months, even if the prices are generous enough to support them economically.  That's why the auction is always held 3 years in advance, in order to give time for new generation to be built to reduce auction prices.

Instead, we're looking at a transmission bandaid to keep the existing generation flowing to the places that need it.  And PJM has opened another transmission planning window to add another 4,500MW of generation imports to Northern Virginia because there is no generation currently proposed to fill that need.

Eventually, if PJM's market signal works as intended, new generation will be built near the load.  However, certain states like Virginia and Maryland have passed laws that prevent the building of new fossil fuel generation.  That leaves only the nuclear option to supply the outrageous amount of power needed by the data centers.  Can you imagine how long it would take to build a new nuclear plant in Northern Virginia?  It would be completed on the 12th of Never.  Meanwhile, transmission is the only viable option.

PJM's market system didn't work to get generation built in time to meet new need because PJM and FERC had turned it off and were asleep at the switch.  Now we have a disaster of epic proportions on our hands.

What's going to happen first?  The construction of hotly opposed transmission projects, or the building of new generation?  And where will that generation be built?  Continuing to build in PA and WV only perpetuates the transmission problem.  We need new generation at load.  It's probably cheaper than billions of dollars of new transmission, but it takes a willingness to sacrifice for its own benefit on the part of the data center loving states.

New generation is coming to market... and how much of it will obviate the need for new transmission?  That's an unknown at this point, but it's going to happen.  PJM's transmission project needs will change and fall apart.  Let's hold the line, folks!  This battle is far from over!
2 Comments

PJM Sets A Precedent

7/15/2024

0 Comments

 
At its July 9 Transmission Expansion Advisory Committee meeting, PJM proposed a re-route of the MidAtlantic Resiliency Link (MARL).  MARL is a giant extension cord for importing West Virginia coal-fired electricity to Loudoun County's "data center alley." 

Loudoun County just can't stop approving new data centers, even though it has no way to power them.  Now Loudoun's data center addiction is impacting people in other states... people who will have their property taken using eminent domain so that Loudoun can have more electricity for its data centers.  Loudoun County is not going to stop building data centers until its voters MAKE them stop building data centers.  That would happen in a hot minute if Loudoun County's SACRED COWS were impacted by the data centers.

This is the Sacred Cow Zone.  A look at an electric infrastructure map shows a pristine donut hole surrounded by high voltage transmission lines, substations, and generators on all sides.  But there's nothing in the Sacred Cow Zone!
Picture
What's a Sacred Cow?  A person with more money (and therefore more political influence) than you.  Examples include Jackie Kennedy, who took umbrage at a proposal to run a power line through her pony club in the Sacred Cow Zone back in the 1960's.  Legend has it that caused the line to end up in Jefferson County, West Virginia instead.  It's the reason we have that 500kV transmission line right across the middle of our county today.  Another example might be the movie stars and their wine-making friends who objected to a different 500kV high-voltage transmission line in the mid 2000s called TrAIL.  That line got pushed south into Fauquier County instead of impacting the Sacred Cows.

If you want to nauseate yourself a bit you could read the fakeass "report" the Sacred Cows threw together to plead their case that they are much, much too sacred to be impacted by the MARL.  They really think they are much more special than you.  Their views!  Their wine!  Their horses! Their environment!  They even claim to be DC's "central park", where harried rich and important people can go to escape the daily grind of grinding the less fortunate into the dirt.  If they thought they were going to get some sympathy from that report, I suggest it's time to buy a mirror and take a really good look.  Your arrogance is showing and people are laughing at your utter snobbery.  Get over yourself!

Because of Jackie Kennedy's pony club and resident movie stars, PJM was also attuned to the history of the Sacred Cow Zone.  It created a "work around" re-route up front, and now it has pulled the ejector button before even TRYING to propose a route through Loudoun.  It went from this
Picture
to this
Picture
It's a miracle!  The Sacred Cow Zone has been saved again!  However, in doing so, other landowners who were not previously affected are now affected.  In fact, those landowners in Northern Loudoun will have their property taken using eminent domain to widen the existing right of way, as confirmed by FirstEnergy's representative at the meeting.  Those sacrificial lambs get no consideration because they are not rich or important.

You may find it surprising that the Sacred Cow Zone is more important than the C&O Canal National Historical Park!  The re-route crosses the C&O twice whereas the original route didn't cross it at all.  Let's trash a national historical park that regular people from all over the region visit to escape snobbery and selfishness... in favor of snobbery and selfishness.  Is the Sacred Cow Zone really more important than a national park?

What is not really surprising is that the Sacred Cows didn't even think about using their Sacred status to actually help others.  Maybe if they did, they wouldn't be sacred anymore?  In exchange for continuing their Sacred status, the Cows proclaimed their mission:  

To support the overall PJM Regional Transmission Expansion Plan (RTEP) to inter alia supply the rising power needs of the region’s data center industry

Keep that in mind... the Sacred Cows love PJM, transmission lines, and data centers... as long as they are Not In My Back Yard!

And the whole debacle is going to cost all ratepayers in the region $167 MILLION more!  We're going to have to pay $167M to keep the Sacred Cows sacred and free from all that nasty infrastructure needed to power the data centers that keep their tax burden low.  What a world!

The real irony here may be the fact that a transmission line necessary for Loudoun's data centers has been pushed out of Loudoun and onto landowners in other states.
PJM claims it is not setting a precedent by re-routing a transmission line to spare certain rich and powerful people and dump it on others without the resources to fight back.

How are you enjoying the email bombardment, PJM?  The Sacred Cows just couldn't wait to strut their arrogance for the people impacted by the Maryland Piedmont Reliability Project and assure them that if they, too, started having a tantrum at PJM that they could have the transmission line moved out of their community, also.

See?  I'm already right about that.  PJM IS setting a precedent that if you don't want a transmission line in your community you simply have to make some demands and pull the ejector button and you're spared, like magic!  But if PJM is NOT setting a precedent, like Stu assured me they were not last week, then PJM is going to have to explain to those folks in Maryland why they are not Sacred Cows that deserve special treatment.  What'll it be, PJM?
0 Comments

FirstEnergy Files For Incentives For MARL, Delays Project

7/3/2024

0 Comments

 
Picture
The MidAtlantic Resiliency Link, or MARL, transmission project has been assigned by PJM Interconnection to two different transmission builders.  NextEra is assigned to build the majority of it, but FirstEnergy ended up with the portion that runs through Frederick County, VA and Jefferson County, WV.

Long ago, even before PJM ordered MARL, NextEra filed an application for transmission incentives with the Federal Energy Regulatory Commission.  FERC approved them back in January.  Nobody bothered to get involved and comment or protest.

Everyone's been treading water, waiting to get more information, but neither NextEra or FirstEnergy has held public meetings to share information with impacted communities.  Seems like nobody is in a hurry at all.

Remember that when PJM ordered MARL, it said the project was needed to be operating by June 1, 2027 or else there would be darkness.

Back in May, FirstEnergy finally got around to requesting transmission incentives for its portion of the MARL.  It asked FERC to grant it the abandoned plant incentive.  Grant of the abandoned plant incentive begins the tally of project costs that can be recovered if the project is abandoned (cancelled) before being built.  Anything FirstEnergy spends before receiving this incentive is only eligible to be recovered at 50%.  That would mean that FirstEnergy could only collect half of the money it spends on MARL in the case of abandonment.  The other half would come out of FirstEnergy's pocket.  Fitting, don't you think, since FirstEnergy insisted on being assigned this portion that rebuilds and expands lines FirstEnergy already owns?  However, that's not what FirstEnergy asked FERC for... it asked FERC to allow it to recover 100% of whatever it has spent (plus interest) if the project is abandoned.

FERC Commissioner Mark Christie is at war against certain transmission incentives.  FERC opened a rulemaking to examine and revise its incentives more than 4 years ago, but has punted it to the side without action, allowing the overly generous incentives to continue.  
​
I'm taking this opportunity to object to FirstEnergy's request for the abandoned plant incentive.  Do they really need it, since they were so eager to have this project that they engineered some secret deal behind the scenes at PJM?  

NextEra's cost cap for MARL (as crappy as it is) did not transfer to FirstEnergy when it took over this section of the project.  FirstEnergy can and will spend however much it wants... currently estimated at $341M for a very short "rebuild" segment.  How much will they actually spend, and how soon will they spend it?  How much spending is planned *before* state approvals, which if denied can cause abandonment?  FERC should place a limit on running up the spending before project approval.

These are the comments I submitted to FERC.
er2401998.pdf
File Size: 112 kb
File Type: pdf
Download File

And here's the worst part!  As part of their filing, FirstEnergy included a copy of its acceptance letter of PJM's designation of a portion of the MARL.  In their acceptance, FirstEnergy has changed the in-service dates for its portion of the MARL.  The Virginia portions (both in Frederick and Loudoun counties) are supposed to be in-service by June 1, 2028, delayed a year from the date PJM said they were needed.  The in-service date for the West Virginia portion in Jefferson County is delayed until June 1, 2030.  That's right... 2030!  MARL is not planned to be completed and transmitting energy until 2030!  That's six years from now!  Are Virginia's data centers going to hang around waiting to build and be connected to the electric grid for another 6 years?

NO!  They won't wait.  They will go somewhere else where they can build a data center and get electric service before 2030.  The bottom may be about to fall out of Virginia's data center craze.

​Here's what FirstEnergy's acceptance letter looks like:
potomac_edison_designated_entity_acceptance_letter.pdf
File Size: 339 kb
File Type: pdf
Download File

Once the in-service date for PJM's transmission projects starts slipping, it often keeps slipping... right off into oblivion.  It can be delayed if expected load doesn't show up (but goes elsewhere). It can be delayed if the utilities run into permitting problems, such as taking a state denial in a NIETC to FERC for permitting.  It can be delayed if the utilities have difficulty procuring project components; there is a huge supply chain issue for transmission components right now.  It can be delayed if there are issues with land acquisition.  It can (and will) be delayed even further.  And, as I said in my comments...
MARL’s in-service date is already slipping. Why is that relevant? Because the electric grid abhors a vacuum. When a planned transmission (or generation) project fails to come online when needed, other projects will take its place. That’s exactly what happened with the PATH project, and what is likely to happen with the MARL project, including the Potomac Edison portion that is the subject of this filing. 
Giving these transmission companies the greenlight to spend as much of our money as they want before they finally abandon MARL many years in the future is not just and reasonable.
This transmission project may never happen, but PJM and the utilities involved feel they should pursue it anyhow. Is that because there are no other options? Or is it because there’s no harm done to them if it fails. All the burden of failure falls on ratepayers, and this encourages the utilities to take more of a chance than they would it they had some skin in the game. Utilities shoulder no risk, while collecting all the rewards. 
​

Consumers have zero control over the project’s risk factors, but they are the ones left holding the bag when it fails. As consumers, we simply cannot afford to continue to financially cover the failures of grid planners and transmission developers simply because we are the one entity without a voice in incentive awards. 
FirstEnergy has asked FERC to approve its incentive request before July 15.  Once consumers have thus insured the reimbursement of FirstEnergy's project spending, then maybe FirstEnergy can actually start working on MARL.

But what happens if FERC doesn't grant this incentive?  Will FirstEnergy still want to build its part of the MARL?  Or will it have to go back to PJM for revision?

​Stay tuned...
0 Comments
<<Previous

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.