Grain Belt Express Wants MO PSC to Toll its Application

6/13/2015

0 Comments

 
Holding this proceeding in abeyance and allowing the Company to obtain such additional information and to work with Staff to develop additional production cost models would prejudice no one.
They also claim it would be "in the public interest" to allow the application to languish in limbo until Grain Belt Express can actually provide the information the Commission asked for back in February.

"The public" has been inconvenienced and financially harmed by Grain Belt Express every day of the past 2 years this thing has been an active threat to their lives and livelihood.  Targeted landowners have been living in stasis, afraid to invest in their properties, unable to sell their properties without disclosing the possible intrusion of a gigantic power line that will lower its value.  Thousands have been spent legally defending their rights.  There has been many a sleepless night, an uneaten meal, and way too much family time foregone in favor of meetings, hearings, and other related events.  These folks have been put through the wringer, but they have persevered.

Now, when denial of Clean Line's application is imminent, the company suddenly wants the Commission to slow down, after urging it to hurry up all these months it thought it was on the way to victory.

The Commission has given GBE way too many chances already.  A full evidentiary hearing was held.  The record was closed.  But, the Commission gave GBE a second chance to supplement the record months after the record had closed.  Clean Line couldn't be bothered to provide the necessary information or evidence.  Now GBE wants a third chance to get it right, and for thousands of affected landowners to continue to live in suspended animation for however long it takes GBE to get its act together.


Obviously Lawlor's threats to march right to the U.S. DOE to revive his application for federal eminent domain authority under Sec. 1222 of the U.S. Energy Policy Act was a big, fat bluff.  He's not going anywhere, except to drop to his knees right there in Missouri and beg for a third chance.

"Do overs" are best left on the playground.  Release the landowners from this corporate game-playing purgatory.  Deny the application.
0 Comments

Citizens' Groups Accuse Puget Sound Energy of Violating FERC Order 1000

6/10/2015

2 Comments

 
Yesterday, The Coalition of Eastside Neighborhoods for Sensible Energy and Citizens for a Sane Eastside Energy, et al, filed a complaint at FERC against Washington State utilities Puget Sound Energy, Seattle City Light, Bonneville Power Administration and ColumbiaGrid.  The complaint alleges that the utilities violated the Federal Power Act, FERC Orders No. 1000, 890 and 2000, and contractual obligations that the respondents made with the Commission that incorporate the referenced Orders, as well as the terms of their respective Open Access Transmission Tariffs.

Whew!  That's a mouthful, huh?  In plain English, it looks like the complainants are accusing Puget Sound Energy of trying to permit and build a transmission project that was not developed in a plan by an independent grid operator (or a reasonable facsimile, since the Northwest doesn't have a traditional RTO/ISO).

ColumbiaGrid is supposed to be taking the place of a RTO for all the named respondent utilities, and according to the complaint, the utilities promised FERC that ColumbiaGrid would serve in a role to make the area Order 1000-compliant.

The complaint alleges that Puget Sound Energy developed its "Energize Eastside" project without proper load flow studies, no study of alternatives, no RFP to evaluate alternate proposals, and that ColumbiaGrid is an entity controlled by its member utilities, including Puget Sound Energy, and does not meet independence requirements for RTOs.

The complaint also alleges that the project is not the "local load flow" project it claims to be (to escape FERC jurisdiction) but also includes a new 1500MW transmission path to Canada that fulfills a decades-old agreement about shared hydro resources.  The addition of the Canadian firm capacity also elevates the project to one that should be regionally allocated, and not charged 100% to local load in the Eastside neighborhoods, as Puget Sound Energy is attempting to do.

Sounds complicated, but the affidavit of J. Richard Lauckhart is a great read to get an easy handle on the problem here.  These guys really did their homework on FERC process and policies, and provided evidence in the form of expert testimony.  Well done!

Looking forward to seeing where this leads...
2 Comments

Kinder Morgan Owns FERC in Audit Fail

6/10/2015

2 Comments

 
A friend sent me a copy of this recent FERC OE audit of Kinder Morgan, Inc.  He found it unusual because there was no dollar amount of refund in it anywhere.  What was the point?

FERC has never met a utility merger it didn't like.  In exchange for some divestiture and a promise not to charge ratepayers for merger costs, FERC approves every merger I've ever read about.

The divestiture is what it is.  It happens, and then it's over.  However, merger costs happen over a period of several years, and may not appear in rates until after the fact.  How does FERC know that the utility has kept its promise and not passed on merger costs to ratepayers?

It audits them.  It's happening a lot more frequently lately, as the Commission has realized that nobody minds their merger cost promise.  "Mistakes" happen.  If an audit doesn't happen, then the utility keeps the money.  If an audit does happen, then the utility says, "Oooops!  My bad!" and refunds the amount FERC recommends.  No penalties happen.

So, it was really no surprise that FERC's OE commenced an audit of Kinder Morgan a couple years after the merger happened.  FERC audits routinely turn up merger costs "accidentally" included in rates.


But what's interesting in Kinder Morgan's case is that although FERC found four different violations of its accounting rules, the corrective action was prospective.

FERC found that Kinder Morgan had incorrectly recorded some maintenance expenses and
incorrectly expensed some abandoned projects.  That ended up pretty much being a wash.  No big deal.  Nobody but a bean counter cares.

But then FERC discovered that Kinder Morgan had not correctly recorded its merger labor costs in special merger accounts. 


KMI stated that it made a corporate decision not to track merger-related labor costs not due to the lack of process or system, but rather due to the fact that management did not consider the labor-related costs to be incremental costs. Also, KMI asserted that no existing employee costs were shifted to merger activities, since all pipelines continued to receive the same level of service before the
merger and all merger activities were completed as well as employees' regular tasks. KMI stated that more than 300 employees made meaningful contributions to merger activities and received a bonus for their efforts.

Audit staff noted that KMI had the requisite processes, accounting practices, and systems to track the cost of labor for merger activities. However, audit staff found written communication specifically instructing employees not to record any labor costs as a cost related to the merger. By not tracking merger-related labor expenses for more than 300 employees, the KMI jurisdictional entities were unable to accurately record the allocation of labor costs to various USofA accounts based on the time engaged in various classes of work during the period of merger activity.

Audit staff also noted that activities for pursuing, considering, and consummating a corporate merger are nonoperating, so their costs should be recorded in Account 426.5, which includes miscellaneous items that are nonoperating in nature. For accounting purposes, the Commission has consistently stated that costs involving mergers of public utilities are nonoperating and are to be recorded in Account 426.5. By not tracking the cost of employees involved in merger activity, the KMI jurisdictional entities could not distinguish the cost of labor related to the merger from labor costs for pipeline operations. As a result, the KMI jurisdictional entities failed to record such costs consistent with their nature, and the entities were unable to properly allocate labor costs to utility and nonutility operations as required by General Instruction No. 10. This resulted in the KMI jurisdictional entities recording internal labor costs in operating expense accounts that should have been recorded in Account 426.5.
While audit staff believes that the KMI jurisdictional entities should have recorded merger-related labor costs in a nonoperating expense account, KMI stated that the accounting misclassification did not affect customers' rates. Audit staff also did not find that this misclassification affected rates for jurisdictional customers.
So, apparently now it's okay for a merging utility to fail to record its merger labor separately, causing a massive transparency fail that not even FERC can figure out?  What was the point of this audit?  Was FERC trying to make KMI admit to certain dollar amount of merger labor cost and failed?  This is clear as mud, but it looks like KMI's deliberate failure to separate its merger labor costs made it impossible for FERC to determine how much labor cost there was, and where it ended up.  I'm not buying that the merger duties didn't cause any additional labor on the part of the employees.  FERC came away empty-handed.  What a waste of time and money!

But wait.. FERC also discovered "several" accounting misclassifications in their dig for merger costs.  Some of the misclassifications were a wash, rate-wise, but FERC still felt the reclass was necessary to bring KMI into compliance.  Some of them, however, were not.  FERC found donations, civil penalties, and environmental legal reserve in accounts that are recovered from ratepayers.  These transactions should always be recorded in accounts that are not recovered from ratepayers.  So, did FERC dig deeper to at least correct this violation and come away with something for ratepayers? 

Nope.  They recommended that KMI "[e]stablish and implement procedures to ensure proper coding and accounting of expenses under Commission regulations."

So, there was a big stare down about merger labor where FERC blinked first, but when FERC actually found some real money here, it didn't bother to correct it.  It gave KMI a pass, as long as it pretended to do better next time.

I hope future audits do better for ratepayers than this one.  FERC's OE isn't helping ratepayers, it's apparently too busy making headlines with banks and traders.
2 Comments

Dollars and Sense

6/3/2015

1 Comment

 
Has Clean Line finally reached its financial tipping point?

I'm sure the initial estimate of development costs for the company's first three transmission line projects (Plains & Eastern, Rock Island and Grain Belt Express) has long since fallen to the wayside.  So far though, Clean Line has been able to sweet talk its investors into injecting more cash when the company runs into trouble and out of money.  But, at some point, these investors are going to have to slap the checkbook shut, cut their losses and move on.  It's not like they're stupid or something, is it?

Clean Line's projects just keep running into more and more trouble.  Instead of moving forward, they're moving in reverse.

For example, take yesterday's indication from the Missouri Public Service Commission that it will deny GBE's application.  How much money was spent on that application process in Missouri?  Millions were wasted.  GBE's angry response was to threaten to revive their parked application for federal eminent domain under Section 1222 of the Energy Policy Act.

How much is that going to cost?  Many millions more!  Another 1222 application is going to very costly, in both time and money.  It's going to add several years to the permitting process and Clean Line is going to pay every penny of the federal government's cost to process the application, including a multi-million dollar NEPA environmental impact statement process.  And still, there's no guarantee.  In fact Clean Line could get several million into this process with Grain Belt Express, only to receive a denial of its other Section 1222 application currently in process on its Plains & Eastern project.  Such a denial would make continuing with Grain Belt's 1222 application a moot point, but the money will have already been spent.

And then what's Clean Line going to do?  Spend millions lobbying Congress to try to pass legislation giving the federal government the authority to usurp state authority to site and permit transmission?  It's not that easy.  It's been tried again and again over the years and has been nothing but an expensive failure.  Another dead end.

Meanwhile, Clean Line has begun the application process for its Grain Belt project at the Illinois Commerce Commission.  Silly Grain Belt has applied under the "expedited" review rule.  This means that the multi-million dollar Illinois permitting process is all going to come due and payable in the next several months (unless GBE gets lucky and the ICC dismisses their application because they're not a public utility).  And what good is an Illinois certificate without a Missouri certificate?  Illinois certificates expire two years from the date of issue.  There's just no way Grain Belt will have completed the Section 1222 process to overrule Missouri's denial before the Illinois certificate expires.

None of the other Clean Line projects are in any better shape.  Rock Island does not have eminent domain authority in Illinois, and the Iowa portion is slogging along the slow track.  New legislation in Iowa could completely derail the project before the IUB even acts.

Plains & Eastern is getting its clock cleaned in the Section 1222 process.  The U.S. DOE has completely mucked up the entire process by failing to perform its review in a legal and transparent manner.

It's becoming more and more obvious that these projects are NEVER going to happen.  It's time to quit giving money to these clowns and collapse the big top they've been performing under.

Clean Line no longer makes financial sense.
1 Comment

Clowns Enliven Annual PJM Circus

5/26/2015

9 Comments

 
I've been trying to keep my nose to the ol' grindstone and ignore the calliope music coming from PJM's "Annual Meeting" in Atlantic City.  But it's really hard to ignore it when a clown scampers across your computer screen before you've even had your morning coffee.

I started my day today with the latest issue of RTO Insider.  I figured it went well with coffee and would be a pleasant way to wake up before going back to work on something that matters.  I love RTO Insider almost as much as chocolate donuts!

Oooops!
Bowring, Gates’ Consultant Spar over PJM Traders’ Obligations on Loopholes

ATLANTIC CITY, N.J. — To shake or not to shake the Money Tree?

That was the question Independent Market Monitor Joe Bowring posed during his Year in Review presentation at PJM’s Annual Meeting last week, setting off a lively debate with one of the consultants that Richard and Kevin Gates, enlisted in their high profile defense against market manipulation allegations.

“If the rules are imperfect, is it OK to do anything not explicitly prohibited?” Bowring asked.

He quickly provided his own answer. “It is not permissible,” he said, citing what he called the “duty” of market participants to inform RTO officials and federal regulators of such “money trees.”
Is this rule supposed to apply equally to every entity FERC regulates?  Doesn't Bowring realize that utilities routinely exploit "unclear" rules in order to pocket a little extra scratch?  If regulated utilities had a duty to report all their "misinterpretation" money trees to FERC, we're going to need a couple more hotlines.  Of course, if the utilities are so busy self-reporting all their shakes (or kicks, flicks, and karate chops) of the "money tree," they might not have time to "accidentally" misinterpret any rules that result in a profit for their shareholders, would they?  Or will they simply have to hire new monkeys to shake the tree, while the old monkeys watch and phone in a report to FERC's hotline?

Utilities large and small routinely interpret FERC rules in incorrect and bizarre ways in order to squeak some additional profit from them.  Except FERC never fines its utility pets $30M when they get caught breaking the rules.  It's all giggle, giggle, hush, hush, slap my wrist, I promise to be good if you overlook this little "misunderstanding."  FERC needs to tighten that shit up and adopt Bowring's "Money Tree Methodology" for everyone!

I do so admire Bowring's enthusiasm.  You go, sport!  I hear there's going to be a vacant spot on the Commission soon!  Maybe you should be Chairman?

What do you suppose caused Bowring's money tree epiphany?  Do you suppose he participated in the "Spa Toccare"* leisure activity in order to relax and clear his mind before giving his report to the membership?
Whatever you do, don't click on the clown picture above.
No, don't do it!

Well, that would explain things then.  Thanks a lot, Joe, for making me snort with laughter before the coffee was even ready to drink.

*Dedicated to undoing the effects of your day, Spa Toccare offers relaxing treatments guaranteed to exhilarate. Here, tensions melt, knots disappear, skin glistens and eyes sparkle. A new you emerges just in time to wave bye-bye to your worldly cares.
9 Comments

WTF is "Pocket Approval" of a Transmission Line?

5/19/2015

4 Comments

 
Journalists are trained to be independent reporters of the facts.  The readers are supposed to take those facts and form their own opinion.  But what happens when a "journalist" tries to spin her opinion as "news?"

"Clean Line receives pocket approval from legislature."
On the heels of lawmakers voting to reject a House bill designed to stop the Grain Belt Express Clean Line project, Michael Skelly, President of Clean Line Energy, visited a Ralls County site of a Grain Belt Express Clean Line’s delivery station, a $100 million facility that proponents say will allow Missourians to receive low-cost, clean power from the Grain Belt Express Clean Line.

The Grain Belt Express Clean Line is a proposed electric power line that will deliver competitively-priced renewable energy to Missouri. The House Energy and Environment Committee voted down House Bill 1027, which would modify provisions relating to eminent domain powers of utilities, on April 28. The bill was sponsored by Rep. Jim Hansen, R-Frankford, who represents Monroe, Lincoln, Pike, and Ralls Counties.
“With the vote this morning, Missouri lawmakers have demonstrated that they stand behind market based solutions to bring low-cost, renewable energy to the state,” said Mark Lawlor, Director of Development for Clean Line Energy. “The Grain Belt Express Clean Line will deliver enough low-cost clean power to Missouri through a direct connection to the electric grid to power 200,000 Missouri homes. We look forward to continuing to work with landowners and community members to develop the project in Missouri in a collaborative way. This project is very important to Missouri’s energy future.”

At the hearing on the bill, supporters spoke of the benefits that the Grain Belt Express Clean Line project would bring to the state and asked legislators to block HB 1027.
According to the Legislative Drafter's Deskbook:  A Practical Guide, a "pocket approval" happens when the President does not sign a bill, but fails to return it to the legislature within 10 days.  In that case, it becomes law through "pocket approval."

Is that what this reporter meant?  That HB 1027 became law because the President failed to return it to the House?  Or is this reporter just desperate to include the words "approval" and "Grain Belt Express" in a headline?

There was no "approval" for Grain Belt Express in Missouri.  The legislature does not have authority to "approve" a transmission project.  "Approval" can only come from the Missouri Public Service Commission, and the Staff of the MO PSC just last week reaffirmed their recommendation that the PSC DENY APPROVAL for Grain Belt Express.

This headline is simply the reporter's opinionated fantasy.  The only thing that actually happened at the legislature is that Clean Line's expensive lobbyists managed to twist enough arms to prevent legislation supported by the people from passing.  Big deal... there's always next year!

The reporter conveniently skips over the fact that GBE won't provide ANY energy to Missouri that is not purchased by an actual utility that serves electric load in the state.
  Evidence at the PSC indicates that there are no utilities stepping up to purchase electricity from GBE's Missouri converter station.

The article also claims:  "Grain Belt Express project moves process forward, receiving public support."

Moves forward?  Forward to where?  GBE is still stuck in the Molasses Swamp waiting for a decision on its application from the MO PSC.  It's not going anywhere.
And where's the proof that GBE has any "public support?"  The evidence at hand indicates that GBE is receiving record public opposition.  This is backed up by the fact that when "Mike" Skelly called a recent press conference at a field in Ralls County, the only "supporters" who showed up were brought in by GBE from many miles away.  On the same day, the Ralls County Commission re-iterated its opposition to GBE, no matter how much of a company man their assessor wants to be in the media.

Here's Block GBE MO's press release that reflects what REALLY happened:
Two Counties Clarify Opposition to Grain Belt:  Chariton and Ralls Legalize Letters of Rescission
Texas based Clean Line Energy, that hopes to build a 750 mile high voltage-transmission line across the state, just hit another snag. Five out of eight counties crossed have now officially rescinded permission for Grain Belt Express to access their county. In Missouri, each county and the Missouri Public Service Commission (PSC) must grant permission to erect any towers.
The staff of the Missouri PSC recommended denying Grain Belt last fall. They stated “Grain Belt Express has not shown it is needed, economically feasible, or promotes the public interest in Missouri”. They also stated, “Section 229.100 RS Mo precludes Grain Belt from building its proposed line without first obtaining the consent of the County Commission in each of the eight counties in northern Missouri where the line would be located.”
Grain Belt questioned the validity of the rescission letters from two counties that were written in the summer of 2014. They stated that Chariton County’s letter had not specifically withdrawn section 229.100 authority or permission to build.
They also stated that Ralls County had said they would consider granting franchise only after the commission approved Grain Belt. Because the county must give permission for the PSC to grant a certificate it created a chicken and egg situation. Grain Belt asked for the Certificate of Convenience and Necessity first and promises to get the consent of each of the counties afterwards.
In response, both Chariton and Ralls County submitted new letters to the PSC to reiterate that Grain Belt does not have permission to build transmission lines in their county.
Ralls County’s new letter reads, in part, “Accordingly, if our grant of authority of August 23rd, 2012 to Grain Belt Express was valid, the County Commission does hereby rescind and revoke any authority granted that date to Grain Belt Express."
Wiley Hibbard, Presiding Commissioner of Ralls County stated, “I, as well as the other two Commissioners in Ralls County, felt it was important that we should restate our opposition to GBE's application to the PSC.
"By pure coincidence, we chose to send our letter to the PSC on the same day GBE held a press conference in Ralls County. It is my understanding that no landowners from Ralls County attended. GBE had to bring a person in from a county many miles away to speak to the press. This will show Grain Belt and the PSC that landowner's rights are very important to the citizens of Ralls County.”
Jennifer Gatrel of Block Grain Belt Express Missouri stated, “We are delighted that five out of eight counties have withdrawn their permission. We are very hopeful that the Missouri PSC will quickly deny Grain Belt and allow landowners to resume our lives."
A reporter who purposely misstates the facts to promote a corporate agenda does so at the peril of her own reputation.

What crap!
4 Comments

S. 1017 Wants to "Improve" Interstate Electric Transmission Facilities

5/16/2015

6 Comments

 
Brace yourselves, Americans, Congress is tinkering with energy policy again!  No good can come of this.  And some idiot has introduced a whole new Sec. 216 (16 U.S.C. 824p) aka Section 1221 of the Energy Policy Act of 2005 that's even worse than its first iteration.

The original, Section 1221, designated the Secretary of Energy to conduct an electric transmission "congestion study" and designate "National Interest Electric Transmission Corridors" (NIETCs) every three years.  Transmission proposed in these designated corridors
was subject to "backstop" permitting by the Federal Energy Regulatory Commission (FERC) in the event a state withheld approval of an application for a permit for more than one year, or lacked the authority to permit the project.

Section 1221 was promptly deconstructed in two federal courts.  When FERC proposed that "withholding approval" included a denial, and that meant it could override a state's denial of an application, the 4th Circuit determined that "withheld approval"
excludes a state's denial of an application, preserving state authority.  In addition, the 9th Circuit determined that DOE did not properly "consult with states" before designating NIETCs, and therefore it vacated the corridors DOE had set in 2009.

Last year, DOE made a half-hearted attempt to produce the 2012 "congestion study," but was resoundingly smacked down by a whole bunch of comments, and hasn't done a thing since.


In practice, Section 1221 has been an abject failure
.

However, the new Section 216, carried to Congress by Sen. Martin Heinrich (D-NM), attempts to fix all that by giving FERC authority to overrule a state denial of a transmission permit and use federal eminent domain authority to take private property.  It also tosses NIETCs out the window as a means to identify worthy transmission projects and replaces them with an RTO/ISO finding that the project is "needed."


Good news:  The new Sec. 216 does not apply to Clean Line in its current form.

Bad news:  The new Sec. 216 will encourage a whole bunch of new transmission projects of questionable necessity, and landowners along existing corridors and/or those owning "open farmland" are always the first targets identified on the ol' transmission routing Etch-A-Sketch.


So, let's look at what the new Sec. 216 says:

(B) FEDERAL AUTHORITY.—The Commission may authorize, in accordance with subsection (d), construction of a high-priority regional transmission project that the Commission finds to be required by the present or future public convenience and necessity and in accordance with this section if--

“(i) a State--

“(I) fails to approve construction and authorize routing of a high-priority regional transmission project not later than 1 year after the date the applicant submits a completed application for authorization to the State;

“(II) rejects or denies the application for a high-priority regional transmission project;

“(III) authorizes the high-priority regional transmission project subject to conditions that unreasonably interfere with the development of a high-priority regional transmission project contrary to the purposes of this section; or

“(IV) does not have authority to approve the siting of the high-priority regional transmission project; or

“(ii) the developer seeking a certificate for construction under subsection (d) does not qualify to apply for State authorization to construct a high-priority regional transmission project because the developer does not serve end-users in the State.
So, FERC can "authorize" a transmission project if a state denies an application or conditions approval in a way the transmission developer doesn't like.  That's not "backstop" or secondary authority, it's usurping state authority in its entirety.  A state must approve, or else.  So, why even bother with the fan dance of state applications at all?  That's just a big waste of time and money.

Tell ya what... if FERC ends up with authority to overrule state transmission permitting decisions, there's going to be a lot more "turn-offs" for Commissioner Norman Bay, because the protestors will have moved "from pipelines to Order 1000."  *Insert laughter here*


Second problem - how these "special" high-priority regional transmission projects are determined:
(1) HIGH-PRIORITY REGIONAL TRANSMISSION PROJECT.—The term ‘high-priority regional transmission project’ means an overhead, submarine, or underground transmission facility, including conductors or cables, towers, manhole duct systems, reactors, capacitors, circuit breakers, static VAR compensators, static synchronous compensators, power converters, transformers, synchronous condensers, braking resistors, and any ancillary facilities and equipment necessary for the proper operation of the facility, that is selected in a regional transmission plan for the purposes of cost allocation under Order Number 1000 of the Commission (or any successor order), including an interregional project selected under that plan.
That's it -- mere selection of and inclusion in a regional transmission plan makes a project "high-priority."  Ummm... does Heinrich know that RTOs include hundreds of projects in their regional plans each year?  "High-priority" over what?  Transmission projects that aren't in a regional plan?  Those are few and far between because they're nearly impossible to build (ain't that right, Clean Line?)  So, every project is going to be a "high-priority" project in this brave, new world?

It's quite obvious that S.1017 intends to "fix" everything that went wrong with the original Sec. 216, including the flawed NIETCs and the ability of a state to deny an application for a transmission project that did not serve its citizens.  But, let's ask ourselves, does it really need fixing?  State approvals aren't the problem with new transmission, it's federal approvals and studies that muck up and delay transmission plans.  In addition, Congress has resolutely refused to make electric transmission siting and permitting a federal responsibility, and will most likely continue to do so.

There seemed to be little love for controversial legislation like S.1017 at Thursday's Senate Energy and Natural Resources Committee hearing.  But, you know how Congress is... they get up to all sorts of hijinks if you don't keep your eye on them, so this bears a bit of babysitting.

One more thing before I wrap this up... where did this legislation come from?

The original Sec. 216 got its purpose from:
(4) In determining whether to designate a national interest electric transmission corridor under paragraph (2), the Secretary may consider whether--
(A) the economic vitality and development of the corridor, or the end markets served by the corridor, may be constrained by lack of adequate or reasonably priced electricity;
(B)
(i) economic growth in the corridor, or the end markets served by the corridor, may be jeopardized by reliance on limited sources of energy; and
(ii) a diversification of supply is warranted;
(C) the energy independence of the United States would be served by the designation;
(D) the designation would be in the interest of national energy policy; and
(E) the designation would enhance national defense and homeland security.
Nothing in there about renewable energy, right?

Now take a look at the purpose of the new Sec. 216:
(a) Policy.—It is the policy of the United States that the national interstate transmission system should be guided by the goal of maximizing the net benefits of the electricity system, taking into consideration--

“(1) support for the development of new, cleaner power generation capacity, including renewable energy generation located distant from load centers;

“(2) opportunities for reduced emissions from regional power production;

“(3) transmission needs driven by public policy requirements established by State or Federal laws (including regulations);


“(4) cost savings resulting from--

“(A) reduced transmission congestion;

“(B) enhanced opportunities for intraregional and interregional electricity trades;

“(C) reduced line losses;

“(D) generation resource-sharing; and

“(E) enhanced fuel diversity;

“(5) reliability benefits, including satisfying reliability standards and guidelines for resource adequacy and system security;

“(6) diversification of risk relating to events affecting fuel supply or generating resources in a particular region;

“(7) the enhancement of competition in electricity markets and mitigation of market power;

“(8) the ability to collocate facilities on existing rights-of-way;

“(9) competing land use priorities, including land protected under Federal or State law;

“(10) the requirements of section 217(b)(4); and

“(11) the contribution of demand side management (including energy efficiency and demand response), energy storage, distributed generation resources, and smart grid investments.
Oh well, lookie there, big wind is reason #1, 2 & 3 for this new legislation.  This isn't about what's good for the people or the environment.  True democratic energy is relegated to reason #11, just an afterthought.  This legislation is designed to line the pockets of big wind and their big transmission developers, and appears to have been written by the funders of their big front group, "Americans for a Clean Energy Grid."  There are no real "Americans" participating in this farce -- it's nothing but a trade group masquerading as a grassroots movement.  Tawdry and unconvincing, but it appears Heinrich was eager to be their legislative minion.  ALEC ain't got nothing on these big green shysters.
6 Comments

Pizza, Ponies, and Prostitutes!

5/12/2015

2 Comments

 
Let's get the profitable infrastructure project party started!
A landowner from southeast Iowa today said he has recorded proof a land agent for the proposed Bakken Pipeline offered to get him an 18-year-old prostitute if he’d grant access rights to his property so the pipeline may pass through.

Hughie Tweedy of Montrose said he recorded two of his conversations with the land agent.
“On these recordings you will hear evidence of my senior pipeline representative offering me not once, not twice, but three times the sexual services of a woman,” Tweedy said, “the last time being a $1200 teenage prostitute.”


Hmm... wasn't it less than 2 weeks ago that Bakken Pipeline owner Dakota Access was investigating different accusations against its land acquisition company?
“If anybody knows of anyone who’s been dealt with unfairly,” Boeyink says, “get the names to me and we will deal with it swiftly.”
I'm thinking Boeyink didn't move too "swiftly."  Or maybe he's been a whirling dervish but simply can't keep up with the unsavory activities of his hired land agents.

Whether it's offering ponies and prostitutes to landowners in exchange for easements, or pizza parties and puppy chow to college students in exchange for signatures on petitions of support, buying public support for infrastructure projects is big business! 

And who do you think is first in line for the free cheese?
“If an old junkyard dog like me was offered the sexual services of little girls to get my hackles down, I wonder what was offered to the powerbrokers of this state to gain their support for silence,” Tweedy said. “Shame, shame, shame.”
Can't add anything to that wisdom.
2 Comments

Does PJM Finally Understand Constructability, Cost Caps and Performance Standards?

4/29/2015

0 Comments

 
While up to my elbows in dirt yesterday, I got a little buzz on my phone telling me that PJM had awarded the Artificial Island project to... LS Power.  I laughed -- loud and hard.  If you laugh in the garden, and nobody is around to hear it, did you really laugh?  Or do your neighbors simply think that you've finally gone off the rails?

PJM's Artificial Island project window has been fraught with problems from the get-go.  The RTO initially awarded the project to one of its favored incumbents, but was set upon by other competitors who made a convincing case that the process was not competitive.

PJM hired some wacky "constructability" study to try to prove that its selection was based on the ease with which the project could be constructed.  That was a big waste of money.  The study failed to note the single, most-important reason projects get delayed -- public opposition!  Opposition is directly related to routing and the physical impact of the project, and the way its public relations are handled -- the worse the transmission developer does
at this, the bigger the resultant opposition.  That's a big, big factor in "constructability."

PJM got schooled on what "constructability" really means.

And the project PJM ultimately selected makes an underground crossing of the Delaware River
and avoids protected wildlife refuges.  Lesson learned, PJM?

Here's your "constructability" checklist, for future reference:

1.  Does this project make use of existing infrastructure that could be upgraded or rebuilt to lessen impact of a new right-of-way?
2.   Can this project be buried along existing or new rights-of-way?
3.  Can this project be avoided entirely with non-transmission alternatives?
4.  What alternatives are there to the project that you can share with the public?

If these things are truly considered, you could avoid the worst part of public opposition and win the "constructability" war.

It's also of note that LS Power proposed a cost cap for its project.  LS Power now has a firm budget for its project.  If it exceeds budget, it's going to have to justify why and beg on bended knee to recover its overruns.  A cost cap also acts as a performance standard.  If LS Power doesn't perform to get this project built on time and within budget
, it does so at its own peril.

Let's hope the cost cap is also a lesson well-learned by PJM.  It's what Congress intended when creating financial incentives for transmission
, and cost caps effectively end the "the more we spend, the more we make" attitude so pervasive in the transmission industry today, to the benefit of electric ratepayers.

Progress?

0 Comments

Clean Line Energy Partners is NOT a Regional Transmission Organization

4/27/2015

9 Comments

 
Knock, knock!
Who's there?
Regional Transmission Organization!
Is it PJM?
No.
Is it MISO?
No.
Is it SPP?
No.
Which Regional Transmission Organization is it?
It's merchant transmission wanna-be Clean Line Energy Partners!
Go away, Clean Line, you're not a Regional Transmission Organization!

The U.S. Department of Energy has finally published Clean Line's third "application" to have the DOE "participate" in its Plains & Eastern Clean Line transmission project in preparation for opening a new 45-day public comment period on non-NEPA issues.  The only thing missing on this pile of make-believe is the golden binding.

This supplemental application is Clean Line's third chance to cure defects in its prior two applications, such as the fact that Sec. 1222 requires that an eligible project:
(2) is consistent with--
(A) transmission needs identified, in a transmission expansion plan or otherwise, by the appropriate Transmission Organization (as defined in the Federal Power Act [16 U.S.C. 791a et seq.]), if any, or approved regional reliability organization;
None of Clean Line's projects are included in a RTO/ISO plan.  In fact, Clean Line hasn't even bothered submitting its projects into any regional planning process for consideration.

So, what did Clean Line do when the DOE asked that it prove its project met the statutory requirements under Sec. 1222?  Clean Line pretends to be a Regional Transmission Organization!
2.2 The proposed Project must be consistent with transmission needs identified, in a transmission expansion plan or otherwise, by the appropriate Transmission Organization (as defined in the Federal Power Act, 16 U.S.C. 791a et seq.) if any, or approved regional
reliability organization

In establishing this criterion, Congress sought to ensure that projects undertaken through Section 1222 are appropriately planned to meet identified transmission needs. The Plains & Eastern Project meets this requirement. On an  interregional basis, numerous planning
initiatives and reports have identified the need for new West-East transmission lines to move
wind power from the central United States to load centers. On a regional basis, SPP and MISO (the two RTOs with which the Project interconnects) have also identified the need for new transmission facilities to accommodate wind generation. Further the Project has been planned and developed in a manner that is consistent with ISO/RTO planning assessments. Namely, in planning and developing the Project, Clean Line performed a series of studies and evaluations that are consistent with how the ISOs and RTOs generally identify needs and solutions for transmission system development. A final measure by which Clean Line meets the statutory requirement is its consistency with reliability standards issued by the approved regional reliability organizations (“RRO”) as envisioned under Section 1222. In light of these multiple areas of consistency, further detailed below, Project meets the criterion for consistency with planning and identified transmission needs.
That's right.  Clean Line says that it planned its project using the same studies that RTOs use to make regional transmission plans, therefore Clean Line's findings that its project meets identified transmission needs are just as good as any RTO determination.

Idiots.
Here's what it takes to be a Regional Transmission Organization:
(j) Required characteristics for a Regional Transmission Organization.
A Regional Transmission Organization must satisfy the following characteristics when it commences operation:
(1) Independence. The Regional Transmission Organization must be independent of any market participant. The Regional Transmission Organization must include, as part of its demonstration of independence, a demonstration that it meets the following:
(i) The Regional Transmission Organization, its employees, and any non-stakeholder directors must not have financial interests in any market participant.
(ii) The Regional Transmission Organization must have a decision making process that is independent of control by any market participant or class of participants.
(iii) The Regional Transmission Organization must have exclusive and independent authority under section 205 of the Federal Power Act (16 U.S.C. 824d), to propose rates, terms and conditions of transmission service provided over the facilities it operates.
Get it, Clean Line?  You can't be a Regional Transmission Organization that identifies transmission needs as long as you have a PECUNIARY interest in a project under consideration.

Clean Line is not a Regional Transmission Organization.

Just one more thing to fight about in federal court?  Any determination by DOE that Clean Line's project(s) qualify under Section 1222 is sort of like one of those Monopoly "Go To Jail" cards.  Go to Federal Court.  Go Directly to Federal Court.  Do Not Pass "Go."  Do not collect... any money at all. 

Do you suppose Clean Line is also going to be on the hook for DOE's legal bills, or is the American Taxpayer going to end up funding this courtroom showdown?
9 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.